Year wise status of schemes implemented under UNTIED fund

    1. Status of schemes sanctioned for the year 2016-2017

      Sl. No. Name of the Schemes Executing Agency (Rs. in Lakh) Physical Progress (in%) Remarks
      Amount Sanctioned  Amount
      Released
      Balance
      Amount
      1 Development of Madhupur Satra as an Epi Centre of Cultural Tourism under Untied Fund for the year 2016-17 PWD(B) 200.00 0.00 200.00   Work in progress. EE PWD(B) has been asked to expedite progress of work vide dtd. 01/03/19
      2 Construction and Renovation of Ex. Chief Minister, Sarat Ch. Sinha Memorial Park/ Auditorium at Chapar under Untied Fund for the year 2016-17 PWD(B) 100.00 57.50849 42.49 75% Work is in progress
      3 Construction of Brick Boundary Wall of Kala Khetra at Golakganj under Untied Fund for the year 2016-17 (Phase-I) 100.00 64.38646 35.61 69% Work is in progress
      4 Construction of Chilarai Park at Golakganj (Bhai Bazar) Chagolia under Untied Fund for the year 2016-17 (Construction of Brick Boundary Wall with Iron Grill) (Phase-I) 50.00 0.00 50.00   Execution of work delayed due to land related issue
      5 Constn. of Class Room along with Lavatory Unit of Sankardev Sishu Niketan, Ward No. 3, Sapatgram under Bilasipara (West) LAC Constuction Committee
      (Headed by H/T Lilananda Bidypith M.E. School)
      10.00 10.00 0.00 100% Work completed
      6 Construction of Modern Toilet Complex at Dhubri -do-
      (Headed by DDC, Dhubri)
      10.00 10.00 0.00 100% Work completed
      7 Construction of Modern Toilet Complex at Gauripur -do-
      (Headed by EE,PWD(B) Dhubri)
      10.00 5.00 5.00 70% Release of 2nd instt. Under process
      8 Construction of Modern Toilet Complex at Bilasipara West -do-
      (Headed by BDO, Mahamaya)
      10.00 10.00 0.00 100% Work completed
      9 Construction of Assam Type Building for Chemistry Laboratory at Chapor Higher Secondary School, Chapor -do-
      (Headed by CO, Chapar)
      15.00 15.00 0.00 100% Work completed. 
      10 Construction of Building of Goalporiya Loko Sanskritik Unnayan Prakalpa at Bilasipara (to be replaced by "Constn of Prachin Bhasa Sanskriti Gabesana Kendra at Bilasipara" -do-
      (Headed by CO, Blp)
      50.00 25.00 25.00   Work is in progress
      11 Development of public field with facility for emergency landing for three Chopper at South Salmara -do-
      (Headed by DDC, Dhubri)
      50.00 37.50 12.50 75% Approval of Working Estimate from T & D Deptt. awaited
      12 Construction of Auditorium at Hatsingimari  PWD(B) 100.00 82.10403 17.90 85% Work is in progress
      13 Construction of Guest House at Mankachar 100.00 52.34 47.66 80% Work is in progress
        Golakganj LAC            
      14 Construction of RCC Single Storied Building of Shankardev Sishu Bidya Niketan, Agomani at Vill.-Kaldoba Pt.-II, P.O. Agomani under Untied Fund for the year 2016-17 Constuction Committee
      (Headed by CO, Glkj.)
      10.00 10.00 0.00 70% 2nd installment released to complete the balance work
      15 Construction of Class Room of Shankardev Sishu Niketan at Vill.-South Tokrerchara Pt.IV, P.O. & P.S. Golakganj under Golakganj Dev. Block under Untied Fund for the year 2016-17 -do- 10.00 10.00 0.00 70% 2nd installment released to complete the balance work
      16 Construction of Class Room & Girls’ Common Room along with Lavatory unit of Shankardev Sishu Bidya Niketan, Baterhat, Vill.-Kaimari, P.S. Golakganj under Agomani Dev. Block  under Untied Fund for the year 2016-17 -do- 10.00 10.00 0.00 70% 2nd installment released to complete the balance work
      17 Construction of Class Room & Girls’ Common Room along with Lavatory unit of Shankardev Sishu Bidya Niketan, Halakura at Vill.-Jinkata Pt.-II P.O. Mahamayahat under Agomani Dev. Block  under Untied Fund for the year 2016-17 -do- 10.00 10.00 0.00 70% 2nd installment released to complete the balance work
      18 Construction of School Building of Shankardev Sishu Niketan, Kachakhana at Vill.-Purni, P.O. Kachakhana under Golakganj Dev. Blockgomani under Untied Fund for the year 2016-17 -do- 10.00 10.00 0.00 70% 2nd installment released to complete the balance work
        Bilasipara (East) LAC            
      19 Construction of Koch Rajbongshi Sanskritik Vikash Kendra in Sasargaon Pt.I Village at Futkibari G.P. under Untied Fund for the year 2016-17  Constuction Committee
      (Headed by CO, Blp)
      11.00 11.00 0.00 100% Work completed. 
      20 Construction of permanent Stage of Chapar Progati Bhawan with both side varenda & Floor of old Building, P.O. Chapar Dist. Dhubri (Assam) under Untied Fund for the year 2016-17     -do-
      (Headed by CO, Chapar)
      15.00 15.00 0.00 100% Work completed. 
      21 Construction of School Building of Sankardev Sishu Niketan, Salkocha Dhubri (Assam) -do-
      (Headed by CO, Chapar)
      10.00 8.00 2.00 80% Work is in progress
      22 Improvement of Padmashri Pratima Barua Pandey Preksha Griha, Bilasipara  -do-
      (Headed by CO, Blp)
      14.00 14.00 0.00 100% Work completed. 
        Gauripur LAC            
      23 Construction of Chain Link Fencing with heavy duty iron gate at Mahamaya Field Gauripur under Untied Fund for the year 2016-17 -do-
      (Headed by DDC, Dhubri)
      10.00 10.00 0.00 100% Work completed
      24 Construction of Class Room Building (A.T.) at Alomganj Rangamati College under Untied Fund for the year 2016-17 -do- 10.00 10.00 0.00 100% Work completed
      25 Construction of Brick Boundary Wall of F.A. Memorial High School at Alomganj under Untied Fund for the year 2016-17 -do- 10.00 10.00 0.00 100% Work completed
      26 Construction of RCC Gallery (Remaining Part) with Boundary Wall at Play Ground of Berbhangi High School at Berbhangi under Untied Fund for the year 2016-17 -do- 10.00 10.00 0.00 100% Work completed
      27 Construction of Gallery at Play Ground & raising of low site of Balajan High School under Untied Fund for the year 2016-17 -do- 10.00 10.00 0.00 100% Work completed
        South Salmara LAC            
      28 Construction of Community Hall for cultural activities at Vill.-Padmeralga Pt.-II under Podmeralga G.P. under Untied Fund for the year 2016-17 -do-
      (Headed by BDO, B/Jarua Dev. Block)
      10.00 5.00 5.00   Work is in progress
      29 Construction of Boundary Wall at Birshing Pt.-I reverine PHC at Birshing Pt.-I under Birshing G.P. under Untied Fund for the year 2016-17 -do- 10.00 10.00 0.00 100% Work Completed
      30 Construction of Additional Class Room of Nilokhiah High School at Nilokhiah G.P. under Untied Fund for the year 2016-17 -do- 10.00 10.00 0.00 100% Work Completed
      31 Construction of Boundary Wall of Salkata Janapriya High Schoolat Salkata under Salkata G.P. under Untied Fund for the year 2016-17 -do-
      (Headed by BDO, South Salmara)
      10.00 10.00 0.00 100% Work Completed
         Mankachar LAC            
      32 Construction of Boundary Wall of Moulana Abul Kalam Azad Junior College at Baghapara   -do-
      (Headed by EE,PWD(B) Dhubri)
      10.00 5.00 5.00   Work is in progress
      33 Construction of CIS-SHED with stage of Srimanta Sankardev Kala Kristi Kendra, Maujhuri -do- 10.00 5.00 5.00   Work is in progress
      34 Construction of Anti Erosion worth with Boulder Patching to protect Jano Kalyan High School, Pipulbari Bazar and boundary wall  -do- 10.00 5.00 5.00   Work is in progress
      35 Construction of Boundary Wall and Teachers’ Common Room at Kalapani Higher Secondary School at Kalapani -do- 10.00 5.00 5.00   Under Joint Inspection
      36 Construction of Boundary Wall at Jhawdanga Junior College -do- 10.00 5.00 5.00   Work is in progress
        Jaleswar LAC            
      37 Construction of Brick Boundary Wall at Jamadarhat Janata H.S. School campus under Jamadarhat Dev. Block -do-
      (Principal, Jamadarhat Janata H.S. School)
      10.00 10.00 0.00 100% Work completed. 
      Total 1055.00 586.84 468.16    

      Status of schemes sanctioned for the year 2017-2018

      Sl. No. Name of the Schemes Executing Agency (Rs. in Lakh) Financial Progress (in %) Physical Progress
      (in %)
      Remarks
      Amount Sanctioned   Amount Released
      (1st Instt.)
      Balance Amount
        DHUBRI LAC              
      1 Construction of Community Hall within the premises of Kalahat Gaon Panchayat (Phase-I) under Untied Fund for the year 2017-18 Construction Committee
      Headed by BDO, Gauipur
      49.99 25.00 24.99 50%   Work is in progress
      2 Construction of Boundary Wall at Bidyapara HS School (150 Mt.) -do- 9.30 4.65 4.65 50%   Release of B.F. under process
      3 Construction of Boundary Wall at Hudurhat Dharmasala HS School (150 Mt.) -do- 9.30 4.65 4.65 50%   Release of B.F. under process
      4 Construction of Library Building at Dharmasala College  -do- 7.95 3.98 3.98 50%   Under Joint Inspection
      5 Construction of Girls’ Common Room at Dharmasala College  -do- 11.45 5.73 5.73     Work is in progress
      6 Infrastructure Development of 2134 No. Poyesti Aironjongla LP School, Kalabari LP School & Construction of Girls’ Toilet at Dharmasala College -do- 5.30 2.65 2.65 50%   Work is in progress
      7 Construction of Additional Class Room at 221 No. Pub Para L.P. School, Kuntirchar Pt.-I -do- 5.20 2.60 2.60 50%   Under Joint Inspection
        GAURIPUR LAC              
      8 Construction of Park with statue of Pratima Pandey Barua at Gauripur Town  Construction Committee
      Headed by EE, PWD(B) Dhubri
      25.00 12.50 12.50 50%   Work is in progress
      9 Construction of Boundary Wall at Alomganj Geramari Amalgamated Higher Secondary School -do- 10.00 10.00 0.00 100% 100% Compleed
      10 Construction of Addl. Class Room at Dampur L.P. Pt.-I School -do- 5.00 2.50 2.50 50%   Under Joint |inspection
      11 Construction of Addl. Class Room at Dhalapara L.P. School, Ghegeralga -do- 5.00 2.50 2.50 50%   Under Joint |inspection
      12 Construction of Public Toilet with running water facility at Beparipatti Chariali -do- 5.00 0.00 5.00     Fund release under process
      13 Construction of Public Toilet with running water facility at Balajan Bazar -do- 5.00 2.50 2.50 50%   Work is in progress
      14 Construction of Boundary Wall & Toilet at 2148 No. Hindi School, Gauripur -do- 5.00 2.50 2.50 50%   Work is in progress
      15 Construction of Boundary Wall at P.C. Institution, Gauripur -do- 5.00 2.50 2.50 50%   Under Joint |inspection
      16 Construction of Addl. Class Room at Sishu Kalyan Prathamik Bidyalaya, Kamlajhar -do- 5.00 5.00 0.00 100% 100% Work Completed
      17 Construction of Mukali Mancha at Debitola High School Field -do- 5.00 2.50 2.50 50%   Under Joint |inspection
        GOLAKGANJ LAC              
      18 Construction of Community Hall cum Museum for Koch Rajbongshi at Golakganj   50.00 25.00 25.00 50%   Work is in progress
      19 Construction of Park with a statue of Bir Chilarai near NH 31 at Golakganj    20.00 10.00 10.00 50%   Work is in progress
      20 Construction of 2 Storied Community Hall at Netaji Bhawan, Golakganj (Ph-1) Ground Floor only    20.00 10.00 10.00 50%   Work is in progress
      21 Construction of Ram Rai Kutir Satra Gate at Agomani    20.00 10.00 10.00 50%   Work is in progress
      22 Construction of Boundary Wall & Statue near Lt. Dinesh Ch. Sarkar Memorial Sishu Udyan, Ratiadaha    10.00 5.00 5.00 50%   Work is in progress
        BILASIPARA EAST LAC              
      23 Construction of Bir Chilarai Bhawan at Jamduar Pt.I, Chirakuta Construction Committee
      Headed by CO, Chapar
      12.00 6.00 6.00 50%   Under Joint Inspection
      24 Construction of RCC Building of Sankardev Sishu Vidya Niketan, Chapar at Bhakatgaon  -do- 12.00 6.00 6.00 50%   Work is in progress
      25 Construction of Open Shed cum Community Hall in the Field near Bahalpur Anchalik Durga Mandir at Boropara Pt.II, Bahalpur -do- 10.00 5.00 5.00 50%   Work is in progress
      26 Infrastructure Development of Schools  I/S DDC, Dhubri 10.00 10.00 0.00 100% 100% Work completed
      27 Construction of Girls’ Common Room with Toilet facilities at Lakhiganj Higher Secondary School Construction Committee
      Headed by CO, Blp.
      6.00 3.00 3.00 50% 75% Under Joint Inspection
      28 Construction of Swami Vivekananda Park at Bilasipara Town BDO, Bilasipara  50.00 12.50 37.50 25%   Work is in progress
      29 Construction of Park with a Statue of Jana Neta Sarat Singha at Chapar BDO, Chapar-Salkocha 10.00 5.00 5.00     Work is in progress
        BILASIPARA WEST LAC              
      30 Construction of Brick Boundary Wall in the North side of Sapatgram College under Untied Fund for the year 2017-18 Construction Committee
      Headed by P.Mazumdar, ADC
      50.00 25.00 25.00 50%   . Work is in progress
      31 Construction of Brick Boundary Wall & Land Development of Ghashbari Senior Madrassa  Construction Committee
      Headed by BDO, Mahamaya.
      10.00 10.00 0.00 100% 100% Completed
      32 Construction of Brick Boundary Wall at Azad ME Madrassa, Barkanda  -do- 5.00 5.00 0.00 100% 100% Completed
      33 Construction of Brick Boundary Wall at Bamuni ME School campus   -do- 10.00 10.00 0.00 100% 100% Completed
      34 Infrastructure Development of School in Balipara West  -do- 25.00 12.50 12.50 50%   Work is in progress
        SOUTH SALMARA LAC              
      35 Construction of Agriculture Godown for the benefit of local farmers of Salkata Bazar Construction Committee
      Headed by BDO, S/Salmara
      7.00 3.50 3.50 50%   Work is in progress
      36 Construction of Addl. Class Room of South Salmara College, South Salmara -do- 8.00 4.00 4.00 50%   Work is in progress
      37 Construction of Block Toilet & Water Supply of Moslabari Kushbari Sr. Madrassa, Noskara -do- 5.00 2.50 2.50 50%   Work is in progress
      38 Construction of Addl. Class Room of MohurircharHigh School, Mohurirchar Construction Committee
      Headed by BDO, B/Jarua
      9.50 9.50 0.00 100% 100% Work completed
      39 Construction of Addl. Class Room of 2260 No. River Block Tiller Char L.P. School, Padmeralga -do- 5.30 2.65 2.65 50%   Work is in progress
      40 Construction of Addl. Class Room of Salmara Uttar Par School, Bahir Salmara  -do- 5.30 2.65 2.65 50%   Work is in progress
      41 Construction of Boundary Wall & Safety Tank of Kasturba Gandhi Balika Vidyalaya, Birshing Jarua -do- 9.90 4.95 4.95 50%   work is in progress
        MANKACHAR LAC              
      42 Construction of Addl. Class Room 3 (three) nos. at Janata H.S. School, Kharuabandha Construction Committee
      Headed by EE, PWD(B) Dhubri
      20.00 0.00 20.00     File transferred to D.C. South Salmara
      43 Construction of Latrine, Urinal & water supply facilities for utility at Sonapur Madrassa premises at Kathalbari G.P. -do- 10.00 0.00 10.00     File transferred to D.C. South Salmara
      44 Construction of Boundary Wall of S. Ali H.S. School, Sukchar  -do- 20.00 0.00 20.00     File transferred to D.C. South Salmara
        JALESWAR LAC              
      45 Construction of Brick Boundary Wall at Chirakuti H.S. School” amounting to Rs. 10.00 Lakhs under Untied Fund for the year 2017-18 Construction Committee
      Headed by CEO, ZP, Dhubri
      10.00 5.00 5.00 50%    Work is in progress
      46 Construction of School Boundary Wall at Kulamuya Nichinpur High School -do-
      Headed by H/M , K.N. High  School
      10.00 5.00 5.00 50%   Work is in progress
      47 Construction of Toilet with Fresh Water Supply at Jamadarhat Janata H.S. School campus  -do-
      Headed by Principal, J.J. H.S. School
      5.00 2.50 2.50 50%   Work is in progress
      Total 628.49 304.00 324.49      

      Status of schemes sanctioned for the year 2018-2019

      Sl. No. Name of the Schemes Executing Agency (Rs. In Lakh) Financial Progress (in %) Physical Progress
      (in %)
      Remarks
      Sanctioned Amount    Amount Released
       
      Balance Amount
        DHUBRI LAC              
      1 Construction of Community Hall along with Boundary Wall at Arfatun Nessa Girls' M.E. Madrassa  under Untied Fund, 2018.-19   49.99 0.00 49.99     A modification proposal submitted by Hon'ble MLA, Dhubri has been sent to T & D Deptt. for consideration
        GAURIPUR LAC              
      2 Construction of Player's Pavillion of Gauripur Sports Association at Mahamaya Field under Untied Fund, 2018.-19   5.00 0.00 5.00     Sanction received on 23/07/2019. Ceiling not yet received. Execution under process
      3 Conastruction of Monikut of Gauripur Kirtan Ghar at Gauripur under Untied Fund, 2018.-19   5.00 0.00 5.00     -do-
      4 Construction of Boundar Wall of Dampur Pt.I Prathom Samaj Kabarsthan   5.00 0.00 5.00     -do-
      5 Construction of Mukali Mancha at Alomganj Rangamati College under Untied Fund, 2018.-19    5.00 0.00 5.00     -do-
      6 Construction of Addl. Class Room at B.U. Memorial Girls High Madrassa under Untied Fund, 2018.-19   5.00 0.00 5.00     -do-
      7 Construction of Mukali Mancha at 384 No. Nowerchar L.P. School Play Ground under Untied Fund, 2018.-19   5.00 0.00 5.00     -do-
      8 Construction of Mukali Mancha at Berbhangi Higher Secondary School Field under Untied Fund, 2018.-19   5.00 0.00 5.00     -do-
      9 Construction of Musafir Khana at Gauripur Ward No. 4 under Untied Fund, 2018.-19   5.00 0.00 5.00     -do-
      10 Construction of Extension Auditorium  Kola Guru Bishnu Rabha at Debitola   5.00 0.00 5.00     -do-
      11 Construction of Kalicharan Brahma Cultural Museum at Kazigaon under Untied Fund, 2018.-19   5.00 0.00 5.00     -do-
        GOLAKGANJ LAC              
      12 Construction of Auditorium at Baterhat High School under Untied Fund, 2018.-19   25.00 0.00 25.00     Implementing Agency not yet recommended
      13 Construction of Assam Type Class Room at Jinkata High School under Untied Fund, 2018-19   25.00 0.00 25.00     Clearance from T & D Deptt under process
      14 Construction of Community Hall near Paglababar Dham, Paglahat  under Untied Fund, 2018-19. EE, PWD(B), Dhubri 5.00 0.00 5.00     EE, PWD(B) has been asked to  implement the scheme
      15 Construction of Community Hall near Burar Dham (Pach Hailla)  under Untied Fund, 2018-19. EE, PWD(B), Dhubri 5.00 0.00 5.00     -do-
      16 Construction of Community Hall at Paglahat Naamghar  under Untied Fund, 2018-19. EE, PWD(B), Dhubri 5.00 0.00 5.00     -do-
      17 Construction of Community Hall at Golakganj Naamghar  under Untied Fund, 2018-19. EE, PWD(B), Dhubri 5.00 0.00 5.00     -do-
      18 Construction of Community Hall at Srimanta Sankardev Sangha (Naamghar), Simlabari under Untied Fund, 2018-19. EE, PWD(B), Dhubri 5.00 0.00 5.00     -do-
      19 Construction of Community Hall at Srimanta Sankardev Sangha (Naamghar), Jinkata under Untied Fund, 2018-19. EE, PWD(B), Dhubri 5.00 0.00 5.00     -do-
      20 Construction of Boundary Wall at Jinkata Rajhuwa Satra under Untied Fund, 2018-19. EE, PWD(B), Dhubri 5.00 0.00 5.00     -do-
      21 Construction of Boundary Wall at Jinkata Na-Satra under Untied Fund, 2018-19. EE, PWD(B), Dhubri 5.00 0.00 5.00     -do-
      22 Construction of Community Hall near Kilarpara Dham, Chagolia under Untied Fund, 2018-19. EE, PWD(B), Dhubri 5.00 0.00 5.00     -do-
      23 Construction of Community Hall at Simlabari Rajhuwa Satra under Untied Fund, 2018-19. EE, PWD(B), Dhubri 5.00 0.00 5.00     -do-
      24 Construction of Martyr Statue at Govt. High School, Bisondoi under Untied Fund, 2018-19 EE, PWD(B), Dhubri 2.96 0.00 2.96     -do-
        BILASIPARA EAST LAC              
      25 Development of Paschim Medhipara Prathamik Vidyalaya under Untied Fund, 2018-19.   25.00 0.00 25.00     Fund release under process
      26 Construction of Girls' Common Room at Chapar Madrassa H.S. School  under Untied Fund, 2018-19.   25.00 0.00 25.00     Fund release under process
      27 Construction of Ratnapith College Auditorium, Bahalpur under Untied Fund, 2018-19.   10.00 5.00 5.00 50%   Work is in progress
      28 Construction of Boundary Wall in respect of Raniganj HS School under Untied Fund, 2018-19.   10.00 0.00 10.00     Fund release under process
      29 Construction of Boundary Wall of Salkocha SHC at Salkocha under Untied Fund, 2018-19.   8.00 0.00 8.00     Fund release under process
      30 Improvement of Nayapara Namghar at W/No. 7, Bilasipara under Untied Fund, 2018-19   4.00 2.00 2.00 50%   Work is in progress
      31 Improvement of Sankari Kristi Vikash Kendra Namghar at W/No. 8, Bilasipara under Untied Fund, 2018-19.    4.00 2.00 2.00 50%   Work is in progress
      32 Construction of Natghar of Bilasipara Rajohuwa Namghar at College Road under Untied Fund, 2018-19   5.00 2.50 2.50 50%   Work is in progress
      33 Improvement of Fieldpara Namghar at W/No. 5, Chapar under Untied Fund, 2018-19    4.00 2.00 2.00 50%   Work is in progress
      34 Improvement of Satyapur Namghar at W/No. 8, Chapar under Untied Fund, 2018-19   4.00 2.00 2.00 50%   Work is in progress
      35 Improvement of Barshi Namghar & Cultural Institute at Barshi under Udmari G.P. under Untied Fund, 2019-20    4.00 2.00 2.00 50%   Work is in progress
      36 Improvement of Namghar of Kola Kristi Centre at Udmari Pt.-V under Udmari G.P. under Untied Fund, 2018-19   4.00 0.00 4.00     Fund release under process
      37 Improvement of Hari Mandir Namghar at Molandubi under Raniganj G.P. under Untied Fund, 2019-20   4.00 0.00 4.00     Fund release under process
      38 Improvement of Ganga Mandir Namghar at Bamundanga under under Bamundanga G.P. under Untied Fund, 2018-19   4.00 0.00 4.00     Bank A/C details of Const. Committee yet to receive
      39 Improvement of Bethabari Shiva Mandir under Chirakuta G.P. under Untied Fund, 2018-19   4.00 0.00 4.00     Const. Committee not yet recommended
      40 Construction of Natghar of Ghunghunikhata Namghar under Futkibari G.P.  under Untied Fund, 2018-19    5.00 0.00 5.00     Const. Committee not yet recommended
      41 Improvement of Raniganj Jagadhatri Mandir under Raniganj G.P. under Untied Fund, 2018-19    4.00 0.00 4.00     Fund release under process
      42 Construction of Boundary Wall of Rokakhata H.S. School Play Ground including earth filling under Untied Fund, 2018-19    10.00 5.00 5.00     Work is in progress
      43 Construction of Boundary Wall of Sub-Dvision Hospital, Bilasipara under Untied Fund, 2018-19    6.00 0.00 6.00     Fund release under process
      44 Construction of Boundary Wall of Phutkibari Primary Health Centre under Untied Fund, 2018-19    6.00 0.00 6.00     Fund release under process
        BILASIPARA WEST LAC              
      45 Constructin of Boundary Wall of Jagirmahal Borgirairpar PHC under Untied Fund, 2018-19 Construction Committee
      .
      5.00 0.00 5.00     Sanction received on  18/7/19. Execution under process
      46 Constructin of Cultural Stage of Namghar at Village Rabantari under Untied Fund, 2018-19  -do- 5.00 0.00 5.00     -do-
      47 Construction of School Building (Class Room) of Hatidhura L.P. School under Untied Fund, 2018-19 -do- 5.00 0.00 5.00     -do-
      48 Construction of Boundary Wall of 1793 No. Valantiarpara L.P. School under Untied Fund, 2018-19 -do- 5.00 0.00 5.00     -do-
      49 Construction of Boundary Wall of Khudnamari Kabarsthan under Untied Fund, 2018-19 -do- 5.00 0.00 5.00     -do-
      50 Construction of Veramara Anchalik Jannatul Maoulana Kabarsthan under Untied Fund, 2018-19 -do- 5.00 0.00 5.00     -do-
      51 Construction of Boundary Wall of Bhelakoba Pt.III Kabarsthan under Untied Fund, 2018-19 -do- 5.00 0.00 5.00     -do-
      52 Infrastructural Devekopment of 50 Nos. schools, Bilasipara West LAC (Part-I) under Untied Fund, 2018-19 -do- 8.00 0.00 8.00     -do-
      53 Infrastructural Devekopment of 47 Nos. schools, Bilasipara West LAC (Part-II) under Untied Fund, 2018-19 -do- 7.00 0.00 7.00     -do-
        JALESWAR LAC              
      54 Construction of Boundary Wall at Airkata High School under Untied Fund for the year 2018-19 Construction Committee
      Headed by 
      10.00 5.00 5.00     Work is in progress
        Total   412.95 27.50 385.45