Sl. No. | Year | Schemes | Name of LAC | Caterories SC / ST / OTHERS |
Amt. Sanction |
Amt. Released | Balance Amount | Remarks |
1 | 2014-15 (Ph - I ) |
Const. of Multi - Purpose Hall at Khalishabhita | Goalpara | Other | 15,00,000.00 | 15,00,000.00 | - | Fund transferred to D.C. Goalpara |
2 | 2014-15 (Ph - I ) |
Const. of Community Hall at Khudrapoitari Jr. College | Goalpara | SC | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. Goalpara |
3 | 2014-15 (Ph - I ) |
Const. of 10 Nos. Ring Well within Balijana Block area @ 3 Nos. at Klayanpur GP , 3 Nos. atBaladmari GP , 2 Nos. at Kumri GP & 2 Nos. at Agia GP | Goalpara | ST | 7,00,000.00 | 7,00,000.00 | - | Fund transferred to D.C. Goalpara |
4 | 2014-15 (Ph - I ) |
Const. of Community Hall at Nolonga near Kanjul Uloom Madrassa | Goalpara | Other | 4,00,000.00 | 4,00,000.00 | - | Fund transferred to D.C. Goalpara |
5 | 2014-15 (Ph - I ) |
Const. of Community Hall at Manashpara near M.E. School | Goalpara | Other | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. Goalpara |
6 | 2014-15 (Ph - I ) |
Const. of Hasilabil village road from Kismot house to Noushad house via Salam House | Goalpara | Other | 4,00,000.00 | 4,00,000.00 | - | Fund transferred to D.C. Goalpara |
7 | 2014-15 (Ph - I ) |
Const. of Community Hall at Bahati Salmara | Goalpara | Other | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. Goalpara |
8 | 2014-15 (Ph - I ) |
Const. of community hall at the premises of Ghewmari M.E. Madrassa | DBB | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
9 | 2014-15 (Ph - I ) |
Protection measures against erosion by the river Brahamputra at Nichmonirchar | Jaleswar | Other | 20,00,000.00 | 20,00,000.00 | - | Work Completed |
10 | 2014-15 (Ph - I ) |
Const. of boundary wall with Land development at Nara Narayana Jr. College | DBB | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
11 | 2014-15 (Ph - I ) |
Const. of road from Newghat, Dilbar Ali house to Mollapara Masjid | DBB | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
12 | 2014-15 (Ph - I ) |
Const. of community hall at Usufia Pre. Sr. Madrassa of Sagalchara | DBB | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
13 | 2014-15 (Ph - I ) |
Const. of Boundary wall of Boalkamri Pt. - I Kabarsthan | BLP W | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
14 | 2014-15 (Ph - I ) |
Const. of boundary wall at Andabari Kalairchar Jahanur Islamia Madrassa | BLP W | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
15 | 2014-15 (Ph - I ) |
Const. of boundary wall of Kownbari Jhaupara Iddgah | BLP W | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
16 | 2014-15 (Ph - I ) |
Const. of Addl. Class Room at Futkibari Hihg School | BLP E | SC & ST | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
17 | 2014-15 (Ph - I ) |
Const. of RCC building ( Assam Type ) of Jamiyat Model School at Chokapara | BLP E | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
18 | 2014-15 (Ph - I ) |
Const. of community hall of Masaneralga Adarsha Samaj Kalyan Samity | BLP E | SC | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
19 | 2014-15 (Ph - I ) |
Const. of boundary wall of Tilapara High School | BLP E | SC | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
20 | 2014-15 (Ph - I ) |
Protection measures against erosion by the river Brahamputra at Sotokolia Pt - II | SSM | Other | 20,00,000.00 | 20,00,000.00 | - | Work Completed |
21 | 2014-15 (Ph - I ) |
Const. of community hall at the premises of Satrasal GP Office | GKG | SC | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
22 | 2014-15 (Ph - I ) |
Const. of community hall at Khekshiali Samshanghat Depdhapi G.P | GKG | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
23 | 2014-15 (Ph - I ) |
Protection measures against erosion by the river Brahamputra at Nilokhia Pt - III | SSM | Other | 17,00,000.00 | 17,00,000.00 | - | Work Completed |
24 | 2014-15 (Ph - I ) |
Const. of community hall at Majerchar | SSM | Other | 3,00,000.00 | 3,00,000.00 | - | Work Completed |
25 | 2014-15 (Ph - I ) |
Protection measures against erosion by the river Brahamputra at Kokradanga Pt - I | MKR | Other | 40,00,000.00 | 40,00,000.00 | - | Work Completed |
26 | 2014-15 (Ph - I ) |
Const. of Market shed at Fulkakata Bazar | SSM | Other | 6,00,000.00 | 6,00,000.00 | - | Work Completed |
27 | 2014-15 (Ph - I ) |
Const. of Addl. Class room at the premises of Mohurirchar High School | SSM | Other | 2,00,000.00 | 2,00,000.00 | - | Work Completed |
28 | 2014-15 (Ph - I ) |
Construction of Boundary Wall at Sindurai Madrassa | GKG | SC | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
29 | 2014-15 (Ph - I ) |
Land development at the premises of Dist. Handicaped Unnayan Suruksha Samity at Balajan | Gauripur | SC | 2,00,000.00 | 2,00,000.00 | - | Work Completed |
30 | 2014-15 (Ph - I ) |
Const. of RCC / Assam Type community hall at the premises of Rahmatganj Hafizia Madrassa | GKG | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
31 | 2014-15 (Ph - I ) |
Const. of community hall at the premises of Darul Uloom Adabari Pt - I | DBB | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
32 | 2014-15 (Ph - I ) |
Const. of Permanent stage for addressing Public Meeting at Nayeralga High School Playground | BLP W | Other | 10,00,000.00 | 10,00,000.00 | - | Work Completed |
33 | 2014-15 (Ph - II ) |
Cost. of B/Wall near Simlabari Anchalik Iddgah under Puthimari GP | BLP E | Other | 3,00,000.00 | 3,00,000.00 | - | Work Completed |
34 | 2014-15 (Ph - II ) |
Impv. of road from Anowar Hussain House towards Niranjan Das House under Anandanagar Bangalipara GP | BLP E | SC | 3,00,000.00 | 3,00,000.00 | - | Work Completed |
35 | 2014-15 (Ph - II ) |
Const. of B/Wall near Alhaj Md. Tayub Ali Iddgah Maidan at Vill. Noonmati Under Geravita GP | BLP E | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
36 | 2014-15 (Ph - II ) |
Construction of Community Hall at the premises of Tilapara L.P. School of vill. Khudigaon Pt-II | BLP E | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
37 | 2014-15 (Ph - II ) |
Const. of boundary wall with Irongate at Charaikhola near Bidhuti Roy house at Bisondai GP under Golakganj Dev. Block | GKG | SC | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
38 | 2014-15 (Ph - II ) |
Const. of Dormetory Hall at the Premises of Gajarikandi ( Kukurmara PHC ) | MKR | Other | 14,00,000.00 | 14,00,000.00 | - | Work Completed |
39 | 2014-15 (Ph - II ) |
Extn. of Community Hall ( RCC2 storied Building ) at the premises of Ahmed ali Hafizia Kharizia Madrassa Medartari GP | Jaleswar | Other | 10,00,000.00 | 10,00,000.00 | - | Work Completed |
40 | 2014-15 (Ph - II ) |
Const. of Community Hall at the premises of H.M. High Madrassa | Gauripur | Other | 2,50,000.00 | 2,50,000.00 | - | Work Completed |
41 | 2014-15 (Ph - II ) |
Extn. of Earth filling of Progressive Unit Halakura | GKG | SC | 3,00,000.00 | 3,00,000.00 | - | Work Completed |
42 | 2014-15 (Ph - II ) |
Impv. of Alomganj Rangamari College | Gauripur | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
43 | 2014-15 (Ph - II ) |
Const. of boundary wall of New Hatipota High School | BLP E | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
44 | 2014-15 (Ph - II ) |
Impv. of road from Bamunpara PMGSY road to South Manullapara | MKR | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
45 | 2014-15 (Ph - II ) |
Improvement of Road from Jalauddin house to Mohiron Nessa house of village Sialtari Champaibil, Thakuranbari G.P. | MKR | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
46 | 2014-15 (Ph - II ) |
Protection measures against erosion by the river Kalo at village Kumargati | MKR | Other | 7,50,000.00 | 7,50,000.00 | - | Work Completed |
47 | 2014-15 (Ph - II ) |
Const. of RCC building at the campus of B.N.College, Dhubri | DBB | Other | 1,00,00,000.00 | 1,00,00,000.00 | - | Work Completed |
48 | 2014-15 (Ph - II ) |
Const. of Running Water Supply facilities at Hashdoba | Goalpara | Other | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. Goalpara |
49 | 2014-15 (Ph - II ) |
Const. of Toilet Block at Kaljani near Madrassa | Goalpara | Other | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. Goalpara |
50 | 2014-15 (Ph - II ) |
Const. of Boundary Wall at Kalyanpur Arabic College | Goalpara | Other | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. Goalpara |
51 | 2014-15 (Ph - II ) |
Const. of Class Room of Goalpara Law College ( Ph - II ) | Goalpara | ST & SC | 4,00,000.00 | 4,00,000.00 | - | Fund transferred to D.C. Goalpara |
52 | 2014-15 (Ph - II ) |
Const. of Community Hall at Rajapara under Agia GP | Goalpara | ST | 4,00,000.00 | 4,00,000.00 | - | Fund transferred to D.C. Goalpara |
53 | 2014-15 (Ph - II ) |
Const. of road at Azadnagar with boulder retaining wall of by lane no. 3 of ward no. 19 | Goalpara | Other | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. Goalpara |
54 | 2014-15 (Ph - II ) |
Impv. of Ambari Borbhita road form Ch. 7380 m to Ch. 8100 m. | Goalpara | Other | 10,00,000.00 | 10,00,000.00 | - | Fund transferred to D.C. Goalpara |
55 | 2014-15 (Ph - II ) |
Const. of boundary wall of Sakumari Kabarsthan | Goalpara | Other | 4,00,000.00 | 4,00,000.00 | - | Fund transferred to D.C. Goalpara |
56 | 2014-15 (Ph - II ) |
Const. of class room of Sakina Khatun Senior madrassa , Nabagata | Goalpara | Other | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. Goalpara |
57 | 2014-15 (Ph - II ) |
Impv. Of Playground of Janaklyan ME School, 2 No. Baladmari char | Goalpara | Other | 3,00,000.00 | 3,00,000.00 | - | Fund transferred to D.C. Goalpara |
58 | 2014-15 (Ph - II ) |
Const. of toilet block at Shimlabari near madrassa | Goalpara | Other | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. Goalpara |
59 | 2014-15 (Ph - II ) |
Const. of Patient Waiting Shed with toilet at Lakhipur PHC | Goalpara | SC / ST | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. Goalpara |
60 | 2014-15 (Ph - II ) |
Const. of boundary wall of Mariamnagar Public Field | Goalpara | ST | 3,00,000.00 | 3,00,000.00 | - | Fund transferred to D.C. Goalpara |
61 | 2014-15 (Ph - II ) |
Const. of boundary wall of Gopinath Bordoloi LP School , Fafanga | Goalpara | SC | 3,00,000.00 | 3,00,000.00 | - | Fund transferred to D.C. Goalpara |
62 | 2014-15 (Ph - II ) |
Const. of boundary wall of Nabajyoty Jatiya Vidyalaya , Helpakhri , Ph - I | Goalpara | Other | 4,00,000.00 | 4,00,000.00 | - | Fund transferred to D.C. Goalpara |
2014-15 (Ph - II ) |
CONTINGENCY | 10,00,000.00 | 10,00,000.00 | - |
Sl. No. | Year | Schemes | Name of LAC | Caterories SC / ST / OTHERS |
Amt. Sanction |
Amt. Released | Balance Amount | Remarks |
1 | 2015-16 ( 2014-15) Int Fund |
Const. of road form Dangujhou to Chaiganda Link Road | GKG | ST | 3,00,000.00 | 3,00,000.00 | - | Work Completed |
2 | 2015-16 ( 2014-15) Int Fund |
Const. of road from Patharchabi Link road to Musuljhora Market with CC Block | GKG | ST | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
3 | 2015-16 ( 2014-15) Int Fund |
Const. of Road from 31 NH to Hazari Jharna LP School with Sand Gravel | GKG | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
4 | 2015-16 ( 2014-15) Int Fund |
Impv. of road from Monoj Kr. House to Kojobari Bote Rabha house | GKG | ST | 3,00,000.00 | 3,00,000.00 | - | Work Completed |
5 | 2015-16 ( Ph - I ) |
Impv. of Dargha Sharif Buildin at Powa Macca , Hajo ,Dist. Kamrup ( rural ) Assam. | Hajo | Other | 10,00,000.00 | 10,00,000.00 | - | Work Completed |
6 | 2015-16 ( Ph - I ) |
Palliative measure to protect of Dhubri Patamari Road cum bundh from the erosion of river Brahmaputra at Jangila | DBB | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
7 | 2015-16 ( Ph - I ) |
Impv. of road from Kalabari Iddgah to Railway Bridge at Falimari Pt - II | DBB | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
8 | 2015-16 ( Ph - I ) |
Const. of Waiting Shad at Jhagrarpar Pt - I near Check Post | DBB | Other | 8,00,000.00 | 8,00,000.00 | - | Work Completed |
9 | 2015-16 ( Ph - I ) |
Impv. of road from Khaibar Ali huse to Railway Gate near Jobed Ali house | Gauripur | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
10 | 2015-16 ( Ph - I ) |
Impv. of road from I.B. Sonkosh Road at 1st K.M. to Anandanagar ( repairing and Back Topping ) | BLP E | SC | 10,00,000.00 | 10,00,000.00 | - | Work Completed |
11 | 2015-16 ( Ph - I ) |
Impv. of road from Abdul Barek house to Rojob Ali house at Hatipota Pt - II | BLP E | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
12 | 2015-16 ( Ph - I ) |
Impv. of road from Krishna Nager PWD road to Amjad Ali house | BLP E | SC | 3,00,000.00 | 3,00,000.00 | - | Work Completed |
13 | 2015-16 ( Ph - I ) |
Const. of boundary wall at Tilapara Anchalik Kaborsthan | BLP E | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
14 | 2015-16 ( Ph - I ) |
Impv. of road from 1107 No. Buchirchar L.P. School to Adom Ali house towards Sagunmari Pt - III | BLP W | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
15 | 2015-16 ( Ph - I ) |
Impv. of road from Dhanpur to Suripara | BLP W | SC | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
16 | 2015-16 ( Ph - I ) |
Impv. of road from Monir Uddin house to Surman Ali house at vill. Baniamari Pt - I | BLP W | Other | 8,00,000.00 | 8,00,000.00 | - | Work Completed |
17 | 2015-16 ( Ph - I ) |
Const. of approach road with a Box Culvert at Dalaneralga Pt - I | BLP W | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
18 | 2015-16 ( Ph - I ) |
Const. of road with Bolder Pitching at Vill. Geramari Pt - I | Gauripur | Other | 10,00,000.00 | 10,00,000.00 | - | Work Completed |
19 | 2015-16 ( Ph - I ) |
Protection and boundary wall at Dalshingeralaga Pt - II Idgah | Gauripur | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
20 | 2015-16 ( Ph - I ) |
Const. of Shed at the premises of Beparipatty Kaborsthan | Gauripur | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
21 | 2015-16 ( Ph - I ) |
Const. of Community Hall at Moterjhar Pre - Senior Madrassa | Gauripur | Other | 3,00,000.00 | 3,00,000.00 | - | Work Completed |
22 | 2015-16 ( Ph - I ) |
Impv. of road from Sabul Hussain house to Border Road via Rustom Ali Sarkar house with Sand gravel at Vill. Lakhimari Pt - II | GKG | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
23 | 2015-16 ( Ph - I ) |
Land development near Char Kumargati Hujurighar of Gaspara GP under Dharmasala Dev. Block | DBB | Other | 2,00,000.00 | 2,00,000.00 | - | Work Completed |
24 | 2015-16 ( Ph - I ) |
Const. of Sanitation Toilet Block with Ojukhana near Ahmadia Rahmania Darul Quran Hafizia madrassa at Adabari Pt - II of Adabari GP under Dharmasala Dev. Block | DBB | Other | 2,00,000.00 | 2,00,000.00 | - | Work Completed |
25 | 2015-16 ( Ph - I ) |
Const. of Boundary wall of Jannatul Baki Kaborsthan at Kherbari Pt - IV, of Bamundanga GP under Agomani Dev. Block | GKG | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
26 | 2015-16 ( Ph - I ) |
Land Dev. of Naskara Chandipara Kabarsthan | SSM | Other | 2,00,000.00 | 2,00,000.00 | - | Work Completed |
27 | 2015-16 ( Ph - I ) |
Const. of Class Room of Goalpara Commerce College | Goalpara | Other | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. Goalpara |
28 | 2015-16 ( Ph - I ) |
Const. of boundary wall of Hatishila Kabarsthan | Goalpara | Other | 4,00,000.00 | 4,00,000.00 | - | Fund transferred to D.C. Goalpara |
29 | 2015-16 ( Ph - I ) |
Const. of Chain Link Fancing of Chunari College | Goalpara | Other | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. Goalpara |
30 | 2015-16 ( Ph - I ) |
Const. of boundary wall of public field of Rajmita near madrassa | Goalpara | Other | 3,00,000.00 | 3,00,000.00 | - | Fund transferred to D.C. Goalpara |
31 | 2015-16 ( Ph - I ) |
Const. of community hall at Jaljalipara under Nabagata Shimlitola Gp | Goalpara | Other | 4,00,000.00 | 4,00,000.00 | - | Fund transferred to D.C. Goalpara |
32 | 2015-16 ( Ph - I ) |
Const. of Rupnagar Bi - lane near Khurshid Ali's house | Goalpara | Other | 2,00,000.00 | 2,00,000.00 | - | Fund transferred to D.C. Goalpara |
33 | 2015-16 ( Ph - I ) |
Const. of boundary wall at Dalgoma Anchalik College Ph - I | Goalpara | SC | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. Goalpara |
34 | 2015-16 ( Ph - I ) |
Const. of boundary wall of lakhipur Girl's High School | Goalpara | ST / SC | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. Goalpara |
35 | 2015-16 ( Ph - I ) |
Const. of Community hall at Shimlabari near Jum Jum Gym Center | Goalpara | Other | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. Goalpara |
36 | 2015-16 ( Ph - I ) |
Const. of boundary wall at Dekdowa Kabarsthan | Goalpara | Other | 3,00,000.00 | 3,00,000.00 | - | Fund transferred to D.C. Goalpara |
37 | 2015-16 ( Ph - I ) |
Const. of road from Ulubari Masjid to Bhalukdubi Ulubari LP School with both side drainage | Goalpara | Other | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. Goalpara |
38 | 2015-16 ( Ph - I ) |
Const. of Boundary Wall of Medhipara Chilarai LP School in lieu of Const. of Waiting Shad at Barmanpara under Dhamar GP | Goalpara | SC / ST | 3,00,000.00 | 3,00,000.00 | - | Fund transferred to D.C. Goalpara |
39 | 2015-16 ( Ph - I ) |
Const. of boundary wall of Simlabari Kabarsthan ( Majar ) | Goalpara | Other | 3,00,000.00 | 3,00,000.00 | - | Fund transferred to D.C. Goalpara |
40 | 2015-16 ( Ph - I ) |
Const. of Class room of Baida College | Goalpara | ST | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. Goalpara |
41 | 2015-16 ( Ph - I ) |
Impv. of Rangsapara Village Road in lieu of Const. of community hall at Rowkhowa bollapuri | Goalpara | Other | 4,00,000.00 | 4,00,000.00 | - | Fund transferred to D.C. Goalpara |
42 | 2015-16 ( Ph - I ) |
Const. of community hall at Jobdirbhita near orphanage house (Char Model ) | Goalpara | Other | 3,00,000.00 | 3,00,000.00 | - | Fund transferred to D.C. Goalpara |
43 | 2015-16 ( Ph - I ) |
Const. of boundary wall of Karbala Public Field Ph - I | Goalpara | Other | 3,00,000.00 | 3,00,000.00 | - | Fund transferred to D.C. Goalpara |
44 | 2015-16 ( Ph - I ) |
Const. of community hall at Tarangapur near Madrassa ( Char Model ) | Goalpara | Other | 3,00,000.00 | 3,00,000.00 | - | Fund transferred to D.C. Goalpara |
45 | 2015-16 ( Ph - II ) |
Const. of Multi - Purpose Hall at Jaleswar Dev. Block Campus | Goalpara | Other | 8,52,000.00 | 8,52,000.00 | - | Fund transferred to D.C. Goalpara |
46 | 2015-16 ( Ph - II ) |
Const. of Class Room of Jawaharlal Neheru M.E. School | Goalpara | SC | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
47 | 2015-16 ( Ph - II ) |
Const. of Class Room of Ahmedia Pre Senior Madrassa , Luptachar | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
48 | 2015-16 ( Ph - II ) |
Const. of boundary wall with Entry gate of Bapupara Shatra | Goalpara | ST / SC | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
49 | 2015-16 ( Ph - II ) |
Const. of Community Hall at Chakla under Karipara | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
50 | 2015-16 ( Ph - II ) |
Const. of Staircase at Hurkakuchi river side near Hakikat Ali's house | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
51 | 2015-16 ( Ph - II ) |
Const. of Boulder Retaining wall at Kharmuza Ujanpara | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
52 | 2015-16 ( Ph - II ) |
Const. of boundary wall with Field development of Goalpara Girls' High School | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
53 | 2015-16 ( Ph - II ) |
Const. of boundary wall of Kurshakati M.E. Madrassa | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
54 | 2015-16 ( Ph - II ) |
Const. of boundary wall of Konasipara LP School | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
55 | 2015-16 ( Ph - II ) |
Const. of Class Room of Nagorpur LP School | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
56 | 2015-16 ( Ph - II ) |
Const. of Boundary wall of Dapkarbhita Kabarsthan | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
57 | 2015-16 ( Ph - II ) |
Const. of Addl. Class Room Saptibari Nasiria Pre Senior Madrassa | Goalpara | Other | 5,88,000.00 | 5,88,000.00 | - | Fund transferred to D.C. Goalpara |
58 | 2015-16 ( Ph - II ) |
Const. of Boundary wall of Paschim Saldowa LP School | Goalpara | Other | 5,88,000.00 | 5,88,000.00 | - | Fund transferred to D.C. Goalpara |
59 | 2015-16 ( Ph - II ) |
Restoration measure to check the bank erosion by the river Bramaputra at Baladmari Char (Madan Bazar area ) Goaplara District. | Goalpara | Other | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. Goalpara |
60 | 2015-16 ( Ph - II ) |
Cost. of boundary wall of P.B. College Girls Hostel under Gauripur T.C. | Gauripur | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
61 | 2015-16 ( Ph - II ) |
Const. of boundary wall at Bilasipara Anchalik Iddgah at Bilasipara | BLP E | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
62 | 2015-16 ( Ph - II ) |
Const. of road from Halangbazar Baghmari PMGSY road at 1467 No. Kandargaon LP School towards Baghmari Anchalik Iddgah field | BLP E | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
63 | 2015-16 ( Ph - II ) |
Impv. of road from Sofior Rahman house towards Kasu Sk house with ICB | BLP E | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
64 | 2015-16 ( Ph - II ) |
Const. of Boundary wall at Chirakuta Anchalik Iddgah field | BLP E | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
65 | 2015-16 ( Ph - II ) |
Const. of boundary wall of Buchirchar ME Madrassa | BLP E | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
66 | 2015-16 ( Ph - II ) |
Const. of boundary wall at Kazaikata People's Multiple Academi HS School | BLP W | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
67 | 2015-16 ( Ph - II ) |
Const. of boundary wall at Ghashbari Kabarsthan | BLP W | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
68 | 2015-16 ( Ph - II ) |
Const. of boundary wall at Bhatigutipara Kabarsthan at Gutipara Pt. - V | BLP W | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
69 | 2015-16 ( Ph - II ) |
Protection cum Land Dev. From Bar Library towards Rajib Gandhi Children Park | DBB | Other | 10,00,000.00 | 10,00,000.00 | - | Work Completed |
70 | 2015-16 ( Ph - II ) |
Const. of Community Hall at the premises of Girls' College Dhubri | DBB | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
71 | 2015-16 ( Ph - II ) |
Const. of Road from Uttar Raipur Railwayline to PWD road | Gauripur | SC | 3,00,000.00 | 3,00,000.00 | - | Work Completed |
72 | 2015-16 ( Ph - II ) |
Const. of RCC waiting shed at Molandubi of Kurshakati VCDC | Gauripur | ST | 3,00,000.00 | 3,00,000.00 | - | Work Completed |
73 | 2015-16 ( Ph - II ) |
Const. of RCC waiting shed at Barvita near PWD road of Debitola VCDC | Gauripur | ST | 3,00,000.00 | 3,00,000.00 | - | Work Completed |
74 | 2015-16 ( Ph - II ) |
Const. of RCC Small Culvert near Balajan Bazar to Water supply | Gauripur | Other | 3,00,000.00 | 3,00,000.00 | - | Work Completed |
75 | 2015-16 ( Ph - II ) |
Anti Water logging from Alomganj Bazar Bustand towards Abdus Samad Talukdar house . | Gauripur | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
76 | 2015-16 ( Ph - II ) |
Land Dev. With boundary wall at Ghageralga Idgah Field | Gauripur | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
77 | 2015-16 ( Ph - II ) |
Const. of boundary wall at Simlabari Kabarsthan at Koimari Pt. - I | GKG | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
78 | 2015-16 ( Ph - II ) |
Const. of boundary wall at Kaimari MV School near Baterhat Bazar at Kaimari Pt. - VII | GKG | SC | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
79 | 2015-16 ( Ph - II ) |
Const. of shed ( Janaza Ghar ) of Gokarpar Rajhuwa Kabarsthan at Tolli Pt. - I | GKG | SC | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
80 | 2015-16 ( Ph - II ) |
Const. of Boundary wall of Dham ( Sanyasi ) at Bisondai Pt. - I | GKG | SC | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
81 | 2015-16 ( Ph - II ) |
Const. of raised Platform at Katiaralga Pt. - III ( for shifting BSF Camp ) | SSM | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
82 | 2015-16 ( Ph - II ) |
Const. of C/Hall at the premises of 1 No. Char Bashirchar LP School | SSM | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
83 | 2015-16 ( Ph - II ) |
Const. of Boundary Wall at 9 No. Sand Block Iddgah Field | SSM | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
84 | 2015-16 ( Ph - II ) |
Const. of Community Hall at Ambari Bhuyanpara H.S. School | SSM | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
85 | 2015-16 ( Ph - II ) |
Const. of boundary wall at Mandalpara Kaborsthan | MKR | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
86 | 2015-16 ( Ph - II ) |
Cosnt. of Land Development at Char Shishumara LP School. | MKR | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
87 | 2015-16 ( Ph - II ) |
Land Dev. of Bhurakata M.E. Madrassa field | MKR | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
88 | 2015-16 ( Ph - II ) |
Constn. of Boundary Wall of Telipara Kaborsthan | MKR | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
89 | 2015-16 ( Ph - II ) |
Const. of Boundary wall at Jhowdanga Kaborsthan | MKR | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
90 | 2015-16 ( Ph - II ) |
Land Dev. Of Kakripara State Dispensary field ground | MKR | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
91 | 2015-16 ( Ph - II ) |
Const. of Wooden Bridge approach road at village Kutirghat | MKR | Other | 23,00,000.00 | 23,00,000.00 | - | Work Completed |
92 | 2015-16 ( Ph - II ) |
Const. of road from Sekherullah High School ( near habibia Hafizia Madrassa ) towards MB Road via Slab Culvert Ph - I ) | DBB | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
93 | 2015-16 ( Ph - II ) Int. Fund |
Impv. Of road from Sukanjhar village to Santipur with C.C. block ( Int. Fund) | GKG | Other | 3,00,000.00 | 3,00,000.00 | - | Work Completed |
94 | 2015-16 ( Ph - II ) Int. Fund |
Const. of Road Agril Bundh to Pocharchar LP School ( Int. Fund) | SSM | Other | 3,00,000.00 | 3,00,000.00 | - | Work Completed |
95 | 2015-16 ( Ph - II ) Int. Fund |
Const. of road from A. Malek house to Moinuddin house of vill. Howrarpar ( Int. Fund) | DBB | Other | 3,80,000.00 | 3,80,000.00 | - | Work Completed |
96 | 2015-16 ( Ph - II ) Int. Fund |
Const. of road from Masem Ali house to Abdullah Sk. House of vill. Kalapakani with Hume pipe ( Int. Fund) | DBB | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
97 | 2015-16 ( Ph - II ) Int. Fund |
Const. of Road from Tojmul Hussain house to Patamari LP School with Small Culvert ( Int. Fund) | DBB | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
98 | 2015-16 ( Ph - I ) |
Const. of Shed at Gauripur Vetenary Hospital | Gauripur | SC | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
99 | 2015-16 ( Ph - I ) |
Const. of Boundary Wall at Sateralga Kabarsthan | Gauripur | Other | 2,00,000.00 | 2,00,000.00 | - | Work Completed |
100 | 2015-16 ( Ph - I ) |
Const. of Road from Siddik Mandal house to Pocharchar LP School via Mosk at Village Pocharchar Pi.III | SSM | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
101 | 2015-16 ( Ph - I ) |
Const. of Community Hall at Ghagmari | SSM | Other | 3,00,000.00 | 3,00,000.00 | - | Work Completed |
102 | 2015-16 ( Ph - I ) |
Const. of RCC small Culvert with approach at vill. Chalakura Poyestirchar | SSM | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
103 | 2015-16 ( Ph - I ) |
Impv. Of road from PWD road to Gadadhar River via Rahman Ali house with Sand Gravel and 2 ( two) nos. hume pipe at village lohajani | GKG | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
104 | 2015-16 ( Ph - I ) |
Const. of boundary wall of Kathalbari Kabarsthan at Vill. Pokalagi Pt. III | GKG | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
105 | 2015-16 ( Ph - I ) |
Const. of C/Hall at Jaruarchar Junior College | SSM | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
106 | 2015-16 ( Ph - I ) |
Const. of Boundary wall of 1267 No. Maiserchar LP School at Vill. Kaldoba | GKG | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
107 | 2015-16 ( Ph - I ) |
Inpv. Of road from Shimalkandi to RBP H.S. School Tumni | SSM | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
108 | 2015-16 ( Ph - II ) |
Const. of Addl. Classroom of Dimatala Pt.II ( Tilapara) LP School ( Cord No. 18020305505) | SSM | Other | 1,00,000.00 | 1,00,000.00 | - | Work Completed |
109 | 2015-16 ( Ph - II ) |
Const. of Addl. Classroom of 1185 No. Nashkara LP School | SSM | Other | 1,00,000.00 | 1,00,000.00 | - | Work Completed |
110 | 2015-16 ( Ph - II ) |
Const. of Addl. Classroom of Majher Alga LP School ( Cord No. 18020324407) | SSM | Other | 1,00,000.00 | 1,00,000.00 | - | Work Completed |
111 | 2015-16 ( Ph - II ) |
Const. of Wooden Bridge approach road at village Kutirghat | MKR | 5,00,000.00 | 5,00,000.00 | - | Work Completed | |
2015-16 ( Ph - II ) |
CONTINGENCY | 10,00,000.00 | 10,00,000.00 | - |
Sl. No. | Year | Schemes | Name of LAC | Caterories SC / ST / OTHERS |
Amt. Sanction |
Amt. Released | Balance Amount | Remarks |
1 | 2016-17 ( Ph - I ) |
Const. of Boundary Wall at Nayapara High Madrassa | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
2 | 2016-17 ( Ph - I ) |
Const. of Community Hall at Karbala in lieu of Const. of Community Hall at Madrassa-E-Ayesha | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
3 | 2016-17 ( Ph - I ) |
Const. of Boundary Wall of Kokira Kabarasthan | Goalpara | Other | 3,92,000.00 | 3,92,000.00 | - | Fund transferred to D.C. Goalpara |
4 | 2016-17 ( Ph - I ) |
Const. of Boundary Wall of Sundarpur Kabarsthan | Goalpara | Other | 3,92,000.00 | 3,92,000.00 | - | Fund transferred to D.C. Goalpara |
5 | 2016-17 ( Ph - I ) |
Impv. Of Cultural Bhawan at Shayamrai Satra | Goalpara | SC | 2,94,000.00 | 2,94,000.00 | - | Fund transferred to D.C. Goalpara |
6 | 2016-17 ( Ph - I ) |
Const. of Community toilet with water supply facility at Nolonga near madrassa in lieu of Const. of RCC Cannel at Nolonga Majerpara | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
7 | 2016-17 ( Ph - I ) |
Const. of Class Room of Chakla ME Madrassa | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
8 | 2016-17 ( Ph - I ) |
Const. of Community Hall near Poitari Bazar Madrassa | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
9 | 2016-17 ( Ph - I ) |
Const. of Boundary Wall of Lakhipur Eidgah | Goalpara | Other | 3,92,000.00 | 3,92,000.00 | - | Fund transferred to D.C. Goalpara |
10 | 2016-17 ( Ph - I ) |
Const. of Boundary Wall of Boro Nichinpur Kabarsthan | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
11 | 2016-17 ( Ph - I ) |
Const. of Boundary Wall of Bhalukmari Tiniali ME Madrassa | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
12 | 2016-17 ( Ph - I ) |
Const. of Boundary Wall of Kaminirbhita LP School | Goalpara | Other | 3,92,000.00 | 3,92,000.00 | - | Fund transferred to D.C. Goalpara |
13 | 2016-17 ( Ph - I ) |
Const. of Boundary Wall of Islampur Rajhuwa Kabarsthan under Matia Dev. Block in lieu of Const. of Boundary Wall of Hilful Fajal Banat Khareji Karikori Madrassa, Gugudoba | Goalpara | Other | 2,94,000.00 | 2,94,000.00 | - | Fund transferred to D.C. Goalpara |
14 | 2016-17 ( Ph - I ) |
Const. of Boundary Wall at Hadigaon Kabarsthan | Goalpara | Other | 2,94,000.00 | 2,94,000.00 | - | Fund transferred to D.C. Goalpara |
15 | 2016-17 ( Ph - I ) |
Protection measures against erosion by the river Gangadhar at Vill. Kaldoba Pt-I | GKG | SC | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
16 | 2016-17 ( Ph - I ) |
Const. of Boundary Wall of Chagolia Balakuti Iddgah Field | GKG | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
17 | 2016-17 ( Ph - I ) |
Const. of Community Hall of Fakhrul Ullum Arabic College ( Title Section ) at Atgharitari | GKG | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
18 | 2016-17 ( Ph - I ) |
Const. of Boundary Wall of Barobari Sr. Madrassa | GKG | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
19 | 2016-17 ( Ph - I ) |
Const. of Shed of Dapurpur Anchalik Kabarsthan | GKG | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
20 | 2016-17 ( Ph - I ) |
Const. of Boundary Wall of Uttar Tokrerchara New Kabarsthan at Vill Uttar Tokrerchara Pt-I | GKG | Other | 3,00,000.00 | 3,00,000.00 | - | Work Completed |
21 | 2016-17 ( Ph - I ) |
Infrastructure Dev. of Samshan Ghat at Araiani Pt-II | BLP W | SC | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
22 | 2016-17 ( Ph - I ) |
Const. of Addl. Class Room at Bantinagar LP School (Char Model) at Noichardhap | BLP W | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
23 | 2016-17 ( Ph - I ) |
Const. of Boundary Wall at Nayeralga Iddgah field near Nayeralga High School. | BLP W | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
24 | 2016-17 ( Ph - I ) |
Const. of Boundary Wall of Boyzeralga Anchalik Kabarsthan at Boyzeralga Pt-III | BLP W | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
25 | 2016-17 ( Ph - I ) |
Const. of Boundary Wall of Pachim Suapata LP School at Suapara Pt-IV | BLP W | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
26 | 2016-17 ( Ph - I ) |
Const. of Culvert with approach at Khudigaon near Soulmari Dong | BLP E | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
27 | 2016-17 ( Ph - I ) |
Const. of Boundary wall of Bahalpur Girls' High School | BLP E | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
28 | 2016-17 ( Ph - I ) |
Const. of Boundary Wall of Hatipota Kabarsthan | BLP E | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
29 | 2016-17 ( Ph - I ) |
Const. of Boundary Wall of 1889 No. Kherdubi LP School | BLP E | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
30 | 2016-17 ( Ph - I ) |
Impv. of road from Sultan Ali house towards IB Sankosh road | BLP E | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
31 | 2016-17 ( Ph - I ) |
Impv. of road from Shernagar PMGSY road to Tayab Ali house | GKG | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
32 | 2016-17 ( Ph - I ) |
Const. of RCC Waiting Shed at Dumardaha Pt-II | Gauripur | Other | 3,00,000.00 | 2,25,000.00 | 75,000.00 | On Going |
33 | 2016-17 ( Ph - I ) |
Const. of RCC Culvert at Sateralga Boraibari GP | Gauripur | Other | 6,00,000.00 | 4,50,000.00 | 1,50,000.00 | On Going |
34 | 2016-17 ( Ph - I ) |
Const. of RCC Culvert at Chapghar Pt-II near Matikuti Bil | Gauripur | Other | 5,00,000.00 | 3,75,000.00 | 1,25,000.00 | On Going |
35 | 2016-17 ( Ph - I ) |
Const. of RCC Culvert at Thuriapahar | Gauripur | ST | 3,00,000.00 | 2,25,000.00 | 75,000.00 | On Going |
36 | 2016-17 ( Ph - I ) |
Const. of Boundary Wall of Balajan Kabarsthan | Gauripur | Other | 3,00,000.00 | 2,25,000.00 | 75,000.00 | On Going |
37 | 2016-17 ( Ph - I ) |
Const. of Wooden Bridge near Gaon-Jhala at Falimari Pt-II | DBB | Other | 6,00,000.00 | 6,00,000.00 | - | Work Completed |
38 | 2016-17 ( Ph - I ) |
Const. of Boundary Wall of Old Iddgah field (Chattan) at Madhusoulmari Pt-I | DBB | Other | 2,50,000.00 | 2,50,000.00 | - | Work Completed |
39 | 2016-17 ( Ph - I ) |
Const. of Community Hall at the premises of Habibia Hafizia Madrassa near Shekherullah High School | DBB | Other | 2,50,000.00 | 1,87,500.00 | 62,500.00 | On Going |
40 | 2016-17 ( Ph - I ) |
Const. of Market Shed at Patamari Bazar | DBB | Other | 2,50,000.00 | 1,87,500.00 | 62,500.00 | On Going |
41 | 2016-17 ( Ph - I ) |
Const. of Boundary Wall of Dharmasala Kabarsthan | DBB | Other | 2,53,000.00 | 2,53,000.00 | - | Work Completed |
42 | 2016-17 ( Ph - I ) |
Cosnt. Of Additional Class room at the premises of Gaspara High School at Kumarghati | DBB | Other | 3,00,000.00 | 3,00,000.00 | - | Work Completed |
43 | 2016-17 ( Ph - I ) |
Const. of Toilet Block of College road near West Naya Masque | DBB | Other | 1,50,000.00 | 1,12,500.00 | 37,500.00 | On Going |
44 | 2016-17 ( Ph - I ) |
Protection work by bouldar Sausage at Vill Kazaikata Pt-V near Kazaikata Madrassa by the river Gourang. (Ph-I) | BLP W | Other | 10,00,000.00 | 10,00,000.00 | - | Work Completed |
45 | 2016-17 ( Ph - I ) |
Protection work by bouldar Sausage at Vill Kazaikata Pt-V near Kazaikata Madrassa by the river Gourang. ( Ph-II) | BLP W | Other | 10,00,000.00 | 7,50,000.00 | 2,50,000.00 | On Going |
46 | 2016-17 ( Ph - I ) |
Protection work by bouldar Sausage at Vill Kazaikata Pt-V near Kazaikata Madrassa by the river Gourang. (Ph-III) | BLP W | Other | 5,00,000.00 | 3,75,000.00 | 1,25,000.00 | On Going |
47 | 2016-17 ( Ph - I ) |
Impv. of approach road at Vill. Dalaneralga Pt-I | BLP W | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
48 | 2016-17 ( Ph - I ) |
Protection measures against erosion by the rvier Brahmaputra at Vill. Boali Pt-I | SSM | Other | 7,50,000.00 | 7,50,000.00 | - | Work Completed |
49 | 2016-17 ( Ph - I ) |
Const. of B/Wall near South College Nagar Jame Masjid (Ph-I ) | DBB | Other | 2,50,000.00 | 1,87,500.00 | 62,500.00 | On Going |
50 | 2016-17 ( Ph - I ) Int Fund |
Impv. of road from Ambari Bhuyapara Chariali towards Josim Uddin House | SSM | Other | 2,40,000.00 | 1,80,000.00 | 60,000.00 | On Going |
51 | 2016-17 ( Ph - I ) |
Const. of C/Hall near the Madrassa of Ishayatu Ullum at village Dimatola Pt.I (Ph-I) | SSM | Other | 2,00,000.00 | 1,50,000.00 | 50,000.00 | On Going |
52 | 2016-17 ( Ph - I ) |
Protection measures against erosion by the river Brahmaputra at village Pampara Chatlarpar . (Ph-I) | SSM | Other | 10,00,000.00 | 7,50,000.00 | 2,50,000.00 | On Going |
53 | 2016-17 ( Ph - I ) |
Const. of raised platform at Bondihana Iddgah Field. (Ph-I) | SSM | Other | 2,50,000.00 | 1,87,500.00 | 62,500.00 | On Going |
54 | 2016-17 ( Ph - I ) Int Fund |
Infrst. Development of play ground field near D.C.'s office Dhubri | DBB | Other | 4,00,000.00 | 4,00,000.00 | - | Work Completed |
55 | 2016-17 ( Ph - I ) |
Const. of Boundar wall at Public High School Playground field Khopati | MKR | Other | 4,00,000.00 | 4,00,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
56 | 2016-17 ( Ph - I ) |
Const. of Community Hall ( Char Model ) near Kaliralga | MKR | Other | 4,00,000.00 | 4,00,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
57 | 2016-17 ( Ph - I ) |
Land Dev. at Diara Bazar | MKR | Other | 4,00,000.00 | 4,00,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
58 | 2016-17 ( Ph - I ) |
Impv. of road from Siddik Ali Master House near PMGSY road to market MRA tyre House | MKR | Other | 4,00,000.00 | 4,00,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
59 | 2016-17 ( Ph - I ) |
Infrastructure Dev. of Kutirghat Nabamilan ME Madrassa | MKR | Other | 4,00,000.00 | 4,00,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
60 | 2016-17 ( Ph - I ) |
Infrastructure of Dev. of Wooden Bridge over kalo river Near Kalapani Outpost. | MKR | Other | 1,20,000.00 | 1,20,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
61 | 2016-17 ( Ph - II ) |
Const. of Boundary wall of Raniganj Ancholik Kabarsthan Under BTAD | BLP E | Other | 3,92,000.00 | 3,92,000.00 | - | Work Completed |
62 | 2016-17 ( Ph - II ) |
Const. if Boundary Wall of Rangamati High School | BLP E | Other | 3,92,000.00 | 3,92,000.00 | - | Work Completed |
63 | 2016-17 ( Ph - II ) |
Const. of Boundary wall of Salkocha Bazar Kabarsthan under BTAD | BLP E | Other | 2,94,000.00 | 2,94,000.00 | - | Work Completed |
64 | 2016-17 ( Ph - II ) |
Const. of Culvert with approach from the house of Ramjan Ali to Mohammad Ali house | BLP E | Other | 3,92,000.00 | 2,94,000.00 | 98,000.00 | On Going |
65 | 2016-17 ( Ph - II ) |
Const. of H.P. Culvert with approach near Abdul Azit house of Bangalipara Pt.II | BLP W | Other | 2,94,000.00 | 2,94,000.00 | - | Work Completed |
66 | 2016-17 ( Ph - II ) |
Const. of Class room of Ghunimari High School (Char Model ) | BLP W | Other | 3,92,000.00 | 2,94,000.00 | 98,000.00 | On Going |
67 | 2016-17 ( Ph - II ) |
Const. of Class room Bagribari Junior College | BLP W | Other | 3,92,000.00 | 3,92,000.00 | - | Work Completed |
68 | 2016-17 ( Ph - II ) |
Const. of Boundary wall of 2058 No. Sarakpara L.P. School | BLP W | Other | 3,92,000.00 | 3,92,000.00 | - | Work Completed |
69 | 2016-17 ( Ph - II ) |
Const. of Boundary Wall of Kabarsthan at Village Tharigram vite | SSM | Other | 4,90,000.00 | 4,90,000.00 | - | Work Completed |
70 | 2016-17 ( Ph - II ) |
Protection measures against erosion by the river Brahmaputra at village Dimatola - Katlamari area ( Ph-I ) | SSM | Other | 4,90,000.00 | 4,90,000.00 | - | Work Completed |
71 | 2016-17 ( Ph - II ) |
Impv. of road from Abdul Hoque house to Anowar Hussain house with Sand Gravel | GKG | Other | 4,90,000.00 | 4,90,000.00 | - | Work Completed |
72 | 2016-17 ( Ph - II ) |
Protection measures against erosion by the river Brahmaputra at Patakata Bazar area (Ph-I) | SSM | Other | 4,90,000.00 | 3,67,500.00 | 1,22,500.00 | On Going |
73 | 2016-17 ( Ph - II ) |
Const. of Comunnity Hall at Chatlarpar Platform | SSM | Other | 4,90,000.00 | 3,67,500.00 | 1,22,500.00 | On Going |
74 | 2016-17 ( Ph - II ) |
Const. of Shed at Fakirganj Parghat Auto Stand | SSM | Other | 1,96,000.00 | 1,47,000.00 | 49,000.00 | On Going |
75 | 2016-17 ( Ph - II ) |
Const. of Boundary wall at Sialmari Kabarsthan | SSM | Other | 2,94,000.00 | 2,20,500.00 | 73,500.00 | On Going |
76 | 2016-17 ( Ph - II ) |
Const. of Sub-way road from Dr. Zakir Hussain road to Abdul Mozid house with C.C. block W/no.9 | DBB | Other | 2,94,000.00 | 2,20,500.00 | 73,500.00 | On Going |
77 | 2016-17 ( Ph - II ) |
Const. of RCC building with Land Dev. at the premises of Chest (T.B) Hospital, Dhubri (Ph-I) | DBB | SC & Gen | 49,00,000.00 | 49,00,000.00 | - | Work Completed |
78 | 2016-17 ( Ph - II ) |
Impv. of Bata Gally road with C.C. Block W/No.7 | DBB | SC | 2,94,000.00 | 2,94,000.00 | - | Work Completed |
79 | 2016-17 ( Ph - II ) |
Const. of Community Hall at the premises of Batapara Pre-Senior Madrassa at Kaimari Pt. I | GKG | Other | 2,94,000.00 | 2,94,000.00 | - | Work Completed |
80 | 2016-17 ( Ph - II ) |
Const. of Boundary wall at Kutibari Iddgah field | GKG | Other | 1,96,000.00 | 1,47,000.00 | 49,000.00 | On Going |
81 | 2016-17 ( Ph - II ) |
Const. of RCC Culvert with approach at village Dumardaha near Soleman Ali House | Gauripur | Other | 4,90,000.00 | 3,67,500.00 | 1,22,500.00 | On Going |
82 | 2016-17 ( Ph - II ) |
Const. of RCC Culvert with approach at Vill. Boraibari Pt. V | Gauripur | Other | 4,90,000.00 | 3,67,500.00 | 1,22,500.00 | On Going |
83 | 2016-17 ( Ph - II ) |
Land Development with CC Block alongwith Toilet block both ladies & Gents at Hatsingimari Bus Stand | MKR | Other | 33,32,000.00 | 33,32,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
84 | 2016-17 ( Ph - II ) |
Impv. of road from Agriculture road towards Railway line at village Dalaneralga Pt.II | DBB | Other | 4,90,000.00 | 3,67,500.00 | 1,22,500.00 | On Going |
85 | 2016-17 ( Ph - II ) |
Const. of Science Laboratory Building at the premises of Goalpara College ( Ph-I ) | Goalpara | Other | 49,00,000.00 | 49,00,000.00 | - | Fund transferred to D.C. Goalpara |
86 | 2016-17 ( Ph - II ) |
Const. of Class Room of Balaikhamar Hasong High School | Goalpara | ST | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
87 | 2016-17 ( Ph - II ) |
Const. of Wash Room with Running water supply facility at Sutarpara Bazar near madrassa | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
88 | 2016-17 ( Ph - II ) |
Const. of Community Hall at Aolatoli | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
89 | 2016-17 ( Ph - II ) |
Const. of Boundary Wall Chitlang LP School | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
90 | 2016-17 ( Ph - II ) |
Const. of Boundary Wall of Kamripara Kabarsthan - 1 | Goalpara | Other | 3,92,000.00 | 3,92,000.00 | - | Fund transferred to D.C. Goalpara |
91 | 2016-17 ( Ph - II ) |
Const. of Community Toilet with water supply facility at Gugudoba near Madrassa. | Goalpara | Other | 3,92,000.00 | 3,92,000.00 | - | Fund transferred to D.C. Goalpara |
92 | 2016-17 ( Ph - II ) |
Const. of Community Toilet at Moriomnagar near Jatiya Bidyalaya. | Goalpara | Other | 1,96,000.00 | 1,96,000.00 | - | Fund transferred to D.C. Goalpara |
93 | 2016-17 Int Fund |
Land Dev. at Daspara Shamshan Ghat, Asharikandi | GAURIPUR | SC | 2,00,000.00 | 2,00,000.00 | - | Work Completed |
94 | 2016-17 Int Fund |
Impv. of road with CC Block near Patakata L.P. School Tiniali towards Zakir Hussain house | SSM | Other | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
95 | 2016-17 ( Ph - II ) |
CONTINGENCY | 10,00,000.00 | 10,00,000.00 | - | Work Completed |
Sl. No. | Year | Schemes | Name of LAC | Caterories SC / ST / OTHERS |
Amt. Sanction |
Amt. Released | Balance Amount | Remarks |
1 | 2017-18 ( Ph - I ) |
Const. of Community Toilet Block at Hashdoba near Madrassa | Goalpara | Other | 4,00,000.00 | 4,00,000.00 | - | Fund transferred to D.C. Goalpara |
2 | 2017-18 ( Ph - I ) |
Const. of Entry Gate with Land Development of Moirakuchi Kabarsthan | Goalpara | Other | 4,00,000.00 | 4,00,000.00 | - | Fund transferred to D.C. Goalpara |
3 | 2017-18 ( Ph - I ) |
Installation of 60 Nos. HTW at Monkola Saildowa, Sundarpara &Beldubi GP area | Goalpara | Other | 7,50,000.00 | 7,50,000.00 | - | Fund transferred to D.C. Goalpara |
4 | 2017-18 ( Ph - I ) |
Const. of Boundary wall of Bagun Police Station | Goalpara | SC | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. Goalpara |
5 | 2017-18 ( Ph - I ) |
Installation of 40 Nos. HTW at Rowkhowa GP area | Goalpara | Other | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. Goalpara |
6 | 2017-18 ( Ph - I ) |
Installation of 40 Nos. HTW at Kalshabhanga GP area | Goalpara | Other | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. Goalpara |
7 | 2017-18 ( Ph - I ) |
Const. of Boundary Wall of Dwarka Gojapara High School | Goalpara | ST | 4,00,000.00 | 4,00,000.00 | - | Fund transferred to D.C. Goalpara |
8 | 2017-18 ( Ph - I ) |
Const. of Primara Village Road | Goalpara | ST | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. Goalpara |
9 | 2017-18 ( Ph - I ) |
Const. of Conference Hall of Goalpara Press Club | Goalpara | Other | 6,00,000.00 | 6,00,000.00 | - | Fund transferred to D.C. Goalpara |
10 | 2017-18 ( Ph - I ) |
Const. of Patient Waiting Shed at 200 Baded Civil Hospital, Goalpara | Goalpara | ST | 3,50,000.00 | 3,50,000.00 | - | Fund transferred to D.C. Goalpara |
11 | 2017-18 ( Ph - I ) |
Const. of Waiting Shed at lakhipur Circle Office | Goalpara | Other | 3,00,000.00 | 3,00,000.00 | - | Fund transferred to D.C. Goalpara |
12 | 2017-18 ( Ph - I ) |
Installation of 40 Nos. HTW at Ujirarchar, Darogaralga, Pakhiura & Basantapur NC | Goalpara | Other | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. Goalpara |
13 | 2017-18 ( Ph - I ) |
Const. of Toilet Block at Tiapara near Madrassa | Goalpara | Other | 3,00,000.00 | 3,00,000.00 | - | Fund transferred to D.C. Goalpara |
14 | 2017-18 ( Ph - I ) |
Const. of Boundary Wall at Uttar Kodal Dhowa Kabarsthan | MKR | Other | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
15 | 2017-18 ( Ph - I ) |
Const. of Boundary Wall at Manullapara Tiniali Anchalik Kabarsthan | MKR | Other | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
16 | 2017-18 ( Ph - I ) |
Land Dev. of Bangirchar Puran Sukchar Koumi Madrassa Play Ground | MKR | Other | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
17 | 2017-18 ( Ph - I ) |
Impv. of road from Jhagrarchar Ala Uddin house to Momin Uddin house at village Vati Jhagrarchar | MKR | Other | 5,00,000.00 | 5,00,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
18 | 2017-18 ( Ph - I ) |
Const. of permanent stage at the premises of Jaruarchar Public High School | SSM | Other | 5,37,000.00 | 5,37,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
19 | 2017-18 ( Ph - I ) |
Const. of Road from Anowar Hussain house to Sambhu Sen house of village Shernagar | GKG | Other | 6,00,000.00 | 6,00,000.00 | - | Work Completed |
20 | 2017-18 ( Ph - I ) |
Protection measures against erosion by the river Tipkai of village Darbesherchar | BLP E | Other | 6,00,000.00 | 6,00,000.00 | - | Work Completed |
21 | 2017-18 ( Ph - I ) |
Impv. of road from Baniamari Pt. Viii to Sankosh at village Baniamari Pt. VIII | BLP E | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
22 | 2017-18 ( Ph - I ) |
Const. of CC Block road from Arun Kumar Das house to Ranjit Basumatary house | BLP E | ST | 6,00,000.00 | 6,00,000.00 | - | Work Completed |
23 | 2017-18 ( Ph - I ) |
Const. of road with CC Block at village Morakura | Gauripur | SC | 6,00,000.00 | 6,00,000.00 | - | Work Completed |
24 | 2017-18 ( Ph - I ) |
Const. of road from Iswar Rabha house to Sujen Rabha house of village Murshuljhora with CC block | GKG | ST | 6,50,000.00 | 6,50,000.00 | - | Work Completed |
25 | 2017-18 ( Ph - I ) |
Const. of road from Pathardubi Link road towards Murshuljhora Bazar with CC Block | GKG | ST | 6,00,000.00 | 6,00,000.00 | - | Work Completed |
26 | 2017-18 ( Ph - I ) |
Const. ofCommunity Hall ( Haj Bhawan) at 3 No. Balurchar near Iddgah Field | DBB | Other | 10,00,000.00 | 10,00,000.00 | - | Work Completed |
27 | 2017-18 ( Ph - I ) |
Protection measures against erosion by the river Gangadhar at village Satsewara | GKG | Other | 7,00,000.00 | 7,00,000.00 | - | Work Completed |
28 | 2017-18 ( Ph - I ) |
Protection measures against erosion by the river Brahmaputra of village Boaliarchar | SSM | Other | 7,00,000.00 | 7,00,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
29 | 2017-18 ( Ph - I ) |
Const. of Community Hall at Nagabandh Bazar | SSM | Other | 4,50,000.00 | 4,50,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
30 | 2017-18 ( Ph - I ) |
Protection measures against erosion by the river Gourang of village Simlabari - Paroura area | BLP E | Other | 7,00,000.00 | 7,00,000.00 | - | Work Completed |
31 | 2017-18 ( Ph - I ) |
Land dev. of Kazipara Kabarsthan | BLP E | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
32 | 2017-18 ( Ph - I ) |
Const. of Community Hall at Radha Gobindo Hari Mandir Ashram at Bisondoi | GKG | SC | 3,50,000.00 | 3,50,000.00 | - | Work Completed |
33 | 2017-18 ( Ph - I ) |
Const. of road from Dampur Road to Dampur Pt. I LP School | Gauripur | Other | 5,00,000.00 | 5,00,000.00 | - | Work Completed |
34 | 2017-18 ( Ph - I ) |
Protection measure against erosion by the river Tipkai at village Chang Bandhakuti area | BLP E | Other | 4,50,000.00 | 4,50,000.00 | - | Work Completed |
35 | 2017-18 ( Ph - I ) |
Const. of Community Hall ner Madinatul Ulum Madrassatul Bannat, Ghunimari | BLP E | Other | 3,50,000.00 | 3,50,000.00 | - | Work Completed |
36 | 2017-18 ( Ph - I ) |
Const. of RCC Building at the premises of Harendra Narayan Seminary H.S. School at Bagribari | BLP E | SC | 19,60,000.00 | 19,60,000.00 | - | Work Completed |
37 | 2017-18 ( Ph - I ) |
Const. of RCC Building at the premises of Ratnapith College | BLP E | ST | 19,60,000.00 | 19,60,000.00 | - | Work Completed |
38 | 2017-18 ( Ph - I ) |
Protection measures against erosion by the river Brahmaputra at village Dimatola Katlamari (Ph. II) | SSM | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
39 | 2017-18 ( Ph - I ) |
Protection measures against erosion by the river Brahmaputra at Patakata Bazar area (Ph. II) | SSM | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
40 | 2017-18 ( Ph - I ) |
Const. of Boundary Wall at Birsing Pt. I Kabarsthan | SSM | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
41 | 2017-18 ( Ph - I ) |
Const. of Boundary Wall at Maajeralga Gurguripara Kabarsthan | SSM | Other | 1,47,000.00 | 1,47,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
42 | 2017-18 ( Ph - I ) |
Const. of market shed at Bhelakuba Bazar | SSM | Other | 1,96,000.00 | 1,96,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
43 | 2017-18 ( Ph - I ) |
Const. of Community Hall at the premises of Radha Gobinda Gita Satra of Kachuarkhas Pt. II | Gauripur | SC | 2,45,000.00 | 2,45,000.00 | - | Work Completed |
44 | 2017-18 ( Ph - I ) |
Const. of Boundary Wall at Bhasani Aironjongla Iddagah field (Ph.I) | DBB | Other | 4,90,000.00 | 4,90,000.00 | - | Work Completed |
45 | 2017-18 ( Ph - I ) |
Const. of Anti Water logging from Monsur Ali house towards Momor Uddin house at Subhash Nagar, W/No.12, Dhubri | DBB | SC | 6,86,000.00 | 6,86,000.00 | - | Work Completed |
46 | 2017-18 ( Ph - I ) |
Const. of road from PMGSY road to 222 No. South Dhubirchar L.P. School | DBB | Other | 5,39,000.00 | 5,39,000.00 | - | Work Completed |
47 | 2017-18 ( Ph - I ) |
Const. of RCC building at the premises of Balajan H.S. School | Gauripur | Other | 19,60,000.00 | 19,60,000.00 | - | Work Completed |
48 | 2017-18 ( Ph - I ) |
Const. of Facilitation Center at the premises of D.C's Office, Dhubri | DBB | Other | 4,90,000.00 | 4,90,000.00 | - | Work Completed |
49 | 2017-18 ( Ph - I ) |
Const. of Community Hall at the premises of Fakirarchar L.P. School | SSM | Other | 2,00,000.00 | 2,00,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
50 | 2017-18 ( Ph - I ) |
Const. of RCC Building at the premises of Alomganj Rangamati College | Gauripur | Other | 19,60,000.00 | 19,60,000.00 | - | Work Completed |
51 | 2017-18 ( Ph - I ) |
Const. of RCC Building at the premises of Pragati College, Agomani. | Gauripur | Other | 19,60,000.00 | 19,60,000.00 | - | Work Completed |
52 | 2017-18 ( Ph - I ) Int. Fund |
Infrastructure Dev. & Lighting of Raja Probhat Chandra Baruah Play Ground and PWD Road, Dhubri | DBB | Other | 3,00,000.00 | 2,25,000.00 | 75,000.00 | On Going |
53 | 2017-18 ( Ph - I ) Int. Fund |
Infrastructure Dev. & Illumination of bye land of Dhubri including Circuit House & Gurudwara, Dhubri | DBB | Other | 2,00,000.00 | 1,50,000.00 | 50,000.00 | On Going |
54 | 2017-18 ( Ph - II ) |
Const. of Drainage from Nazirul Islam House to Abdus Samad House | Goalpara | Other | 3,92,000.00 | 392000.00 | - | Fund transferred to D.C. Goalpara |
55 | 2017-18 ( Ph - II ) |
Const. of Milannagar Santipur Village road from Ead Ali House to Nur Islam House | Goalpara | Other | 3,92,000.00 | 392000.00 | - | Fund transferred to D.C. Goalpara |
56 | 2017-18 ( Ph - II ) |
Const. of Boundary Wall of Bhalukdubi Salbari Garo LP School | Goalpara | ST | 3,92,000.00 | 392000.00 | - | Fund transferred to D.C. Goalpara |
57 | 2017-18 ( Ph - II ) |
Const. of Community Hall of Baleswary field at West Bhelakhamar | Goalpara | ST | 3,92,000.00 | 392000.00 | - | Fund transferred to D.C. Goalpara |
58 | 2017-18 ( Ph - II ) |
Const. of Boundary Wall at Buduchar Public field near Budubuchar Madrassa | Goalpara | Other | 3,92,000.00 | 392000.00 | - | Fund transferred to D.C. Goalpara |
59 | 2017-18 ( Ph - II ) |
Const. of Community Hall at Kalairchar | Goalpara | Other | 3,92,000.00 | 392000.00 | - | Fund transferred to D.C. Goalpara |
60 | 2017-18 ( Ph - II ) |
Const. of Boundary Wall at Salmara Kabarasthan | Goalpara | Other | 3,92,000.00 | 392000.00 | - | Fund transferred to D.C. Goalpara |
61 | 2017-18 ( Ph - II ) |
Const. of Boundary Wall of Pajabhanda LP School | Goalpara | SC | 3,92,000.00 | 392000.00 | - | Fund transferred to D.C. Goalpara |
62 | 2017-18 ( Ph - II ) |
Const. of Boundary Wall of Mohammadia Sr. Madrassa, Dekdowa | Goalpara | Other | 3,92,000.00 | 392000.00 | - | Fund transferred to D.C. Goalpara |
63 | 2017-18 ( Ph - II ) |
Const. of Community Hall at Kodaldowa near Kadaldowa LP School | Goalpara | Other | 3,92,000.00 | 392000.00 | - | Fund transferred to D.C. Goalpara |
64 | 2017-18 ( Ph - II ) |
Const. of Boundary Wall with gate of HMAH Madrassa, Porabhita | Goalpara | Other | 4,90,000.00 | 490000.00 | - | Fund transferred to D.C. Goalpara |
65 | 2017-18 ( Ph - II ) |
Const. of Gaurnagar Jr. College | Goalpara | Other | 4,90,000.00 | 490000.00 | - | Fund transferred to D.C. Goalpara |
66 | 2017-18 ( Ph - II ) |
Const. of Boundary Wall of Dharai Kabarasthan | Goalpara | Other | 4,90,000.00 | 490000.00 | - | Fund transferred to D.C. Goalpara |
67 | 2017-18 ( Ph - II ) |
Const. of Boundary Wall with gate of South Chilarbhita LP School | Goalpara | Other | 4,90,000.00 | 490000.00 | - | Fund transferred to D.C. Goalpara |
68 | 2017-18 ( Ph - II ) |
Const. of Boundary Wall of Karbala ME School | Goalpara | Other | 4,90,000.00 | 490000.00 | - | Fund transferred to D.C. Goalpara |
69 | 2017-18 ( Ph - II ) |
Const. of Boundary Wall of Airkata Balupara Kabarasthan | Goalpara | Other | 4,90,000.00 | 490000.00 | - | Fund transferred to D.C. Goalpara |
70 | 2017-18 ( Ph - II ) |
Const. of Boundary Wall with bolder pitching at Khankai Madani Hafizia Madrassa | Goalpara | Other | 4,90,000.00 | 490000.00 | - | Fund transferred to D.C. Goalpara |
71 | 2017-18 ( Ph - II ) |
Const. of Building at the premises of Golakganj BPHC Hospital, Golakganj | GKG | SC & Gen | 19,60,000.00 | 14,70,000.00 | 4,90,000.00 | On Going |
72 | 2017-18 ( Ph - II ) |
Const. of Road from PWD Road Sindurai to Nisiyat Ali House via Samad Ali House at Vill. Sindurai | GKG | Other | 4,90,000.00 | 4,90,000.00 | - | Work Completed |
73 | 2017-18 ( Ph - II ) |
Const. of Boundary Wall of Gogharpar Aribic College ( Title Section), Sagolia | GKG | Other | 4,90,000.00 | 4,90,000.00 | - | Work Completed |
74 | 2017-18 ( Ph - II ) |
Const. of Boundary Wall at Sankari Sanskrit Kristi Kendra Srimanta Sankardev Sangha at Simlabari | GKG | SC | 5,88,000.00 | 5,88,000.00 | - | Work Completed |
75 | 2017-18 ( Ph - II ) |
Const. of Boundary Wall at Kuti Bhamundanga Idd-Gah-Field | GKG | Other | 2,94,000.00 | 2,94,000.00 | - | Work Completed |
76 | 2017-18 ( Ph - II ) |
Const. of Boundary Wall at Membertari Kabarsthan of Vill. Barundanga | GKG | Other | 4,90,000.00 | 4,90,000.00 | - | Work Completed |
77 | 2017-18 ( Ph - II ) |
Const. of Boundary Wall of Jhaskal Pt.I kabarsthan | GKG | Other | 4,90,000.00 | 4,90,000.00 | - | Work Completed |
78 | 2017-18 ( Ph - II ) |
Impv. of road from Kataltuli PMGSY Road to Kathaltuli High School of Vill. Kaimari | GKG | Other | 98,000.00 | 98,000.00 | - | Work Completed |
79 | 2017-18 ( Ph - II ) |
Const. of Road from Irrigation Canel Road to Sabur Uddin House | Gauripur | Other | 4,90,000.00 | 3,67,500.00 | 1,22,500.00 | On Going |
80 | 2017-18 ( Ph - II ) |
Const. of Boundary Wall at the premises of Arfatun Nessa ME Madrassa | Gauripur | Other | 4,90,000.00 | 3,67,500.00 | 1,22,500.00 | On Going |
81 | 2017-18 ( Ph - II ) |
Const. of Market Shed at Kalapakani Bazar | Gauripur | Other | 9,80,000.00 | 7,35,000.00 | 2,45,000.00 | On Going |
82 | 2017-18 ( Ph - II ) |
Const. of Road from Hazari Gaon link Road towards Pachim Dhubri Kabarsthan | DBB | Other | 4,90,000.00 | 3,67,500.00 | 1,22,500.00 | On Going |
83 | 2017-18 ( Ph - II ) |
Const. of Box Culvert with approach road from Ajoy Nath House towards Jayan Uddin Huse with sand gravel via Abdullah House | DBB | SC | 19,60,000.00 | 14,70,000.00 | 4,90,000.00 | On Going |
84 | 2017-18 ( Ph - II ) |
Const. of road from D.K. Road to Naranarayan Jr. College near Jhagararpar Stadium. | DBB | SC | 4,90,000.00 | 3,67,500.00 | 1,22,500.00 | On Going |
85 | 2017-18 ( Ph - II ) |
Const. of Library room at the premises of Alomganj Rangamati College | DBB | Other | 24,50,000.00 | 18,37,500.00 | 6,12,500.00 | On Going |
86 | 2017-18 ( Ph - II ) |
Const. of RCC Building at the premises of Haji Musafirkhana, Hatsingimari ( South Salmara Dist.) | SSM | Other | 49,00,000.00 | 49,00,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
87 | 2017-18 | CONTINGENCY | 10,00,000.00 | 10,00,000.00 | Work Completed |
Sl. No. | Year | Schemes | Name of LAC | Caterories SC / ST / OTHERS |
Amt. Sanction |
Amt. Released | Balance Amount | Remarks |
1 | 2018-19 ( Ph - I ) |
Const. of Boundary Wall with Fate of Pub Kathuri High Madrassa | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
2 | 2018-19 ( Ph - I ) |
Const. of Drainage from Jaleswar Bazar Tiniali Forujulla House to Moinal House | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
3 | 2018-19 ( Ph - I ) |
Const. of Bolder piching from Jalal House to Khalek House Simlabari | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
4 | 2018-19 ( Ph - I ) |
Const. of Boundary Wall of Chatapara JB LP School | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
5 | 2018-19 ( Ph - I ) |
Const. of Bolder Pitching wall of South Bank Gara river | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
6 | 2018-19 ( Ph - I ) |
Const. of Boundary Wall of Palashbari Kabarsthan | Goalpara | Other | 3,92,000.00 | 3,92,000.00 | - | Fund transferred to D.C. Goalpara |
7 | 2018-19 ( Ph - I ) |
Const. of Boundary Wall at Markula PHC | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
8 | 2018-19 ( Ph - I ) |
Const. of Community Hall at Bashbari New Market | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
9 | 2018-19 ( Ph - I ) |
Const. of Cicle Stand at Ambari Bazar High School | Goalpara | Other | 2,45,000.00 | 2,45,000.00 | - | Fund transferred to D.C. Goalpara |
10 | 2018-19 ( Ph - I ) |
Const. of Boundary Wall of Dosra Ambari ME School | Goalpara | Other | 2,45,000.00 | 2,45,000.00 | - | Fund transferred to D.C. Goalpara |
11 | 2018-19 ( Ph - I ) |
Const. of Boundary Wall at Nolonga Ujanpara LP School | Goalpara | Other | 3,92,000.00 | 3,92,000.00 | - | Fund transferred to D.C. Goalpara |
12 | 2018-19 ( Ph - I ) |
Const. of Boundary Wall at Bapurbhita Jurigaon LP School | Goalpara | Other | 2,94,000.00 | 2,94,000.00 | - | Fund transferred to D.C. Goalpara |
13 | 2018-19 ( Ph - I ) |
Const. of Community Hall at Lezam | Goalpara | Other | 3,92,000.00 | 3,92,000.00 | - | Fund transferred to D.C. Goalpara |
14 | 2018-19 ( Ph - I ) |
Const. of Addl. Class Room at Hujuachar Pt. I | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
15 | 2018-19 ( Ph - I ) |
Const. of Waiting Shed at Balijana Circle Office | Goalpara | SC | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
16 | 2018-19 ( Ph - I ) |
Const. of Drainage at Moliapathar Bazar Rupnagar approach road | Goalpara | Other | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
17 | 2018-19 ( Ph - I ) |
Const. of Goalpara Civil Hospital Doctors' quarter approach road | Goalpara | ST | 4,90,000.00 | 4,90,000.00 | - | Fund transferred to D.C. Goalpara |
18 | 2018-19 ( Ph - I ) |
Const. of RCC Building & Land Development alongwith Boundary Wall at the premises of Barkanda Peoples Academy H.S. School | DBB | SC & Gen | 49,00,000.00 | 36,75,000.00 | 12,25,000.00 | On Going |
19 | 2018-19 ( Ph - I ) |
Const. of RCC Building & Land Development alongwith Boundary Wall at the premises of Bilasipara Sr. Madrassa | BLP E | Other | 49,00,000.00 | 36,75,000.00 | 12,25,000.00 | On Going |
20 | 2018-19 ( Ph - I ) |
Const. of Building at the premises of Balajan Higher Secondary School | Gauripur | SC & Gen | 24,50,000.00 | 18,37,500.00 | 6,12,500.00 | On Going |
21 | 2018-19 ( Ph - I ) |
Const. of Community Hall at Fakirganj Bazar area | SSM | Other | 12,25,000.00 | 9,18,750.00 | 3,06,250.00 | On Going |
22 | 2018-19 ( Ph - I ) |
Const. of Addl. Class Room at the premises of Rowarpar Bhelakoba ME Maddrassa | Birsing Jarua | Other | 2,94,000.00 | 2,20,500.00 | 73,500.00 | On Going |
23 | 2018-19 ( Ph - I ) |
Const. of Boundary Wall at Muthakhowa Iddgah field cum Platform | Birsing Jarua | Other | 4,41,000.00 | 3,30,750.00 | 1,10,250.00 | On Going |
24 | 2018-19 ( Ph - I ) |
Const. of raised Platform at Bondihana Iddgah field. | Birsing Jarua | Other | 2,45,000.00 | 1,83,750.00 | 61,250.00 | On Going |
25 | 2018-19 ( Ph - I ) |
Const. of Community Hall at the premises of Gurguripar Islamia ME Madrassa | Birsing Jarua | Other | 4,90,000.00 | 3,67,500.00 | 1,22,500.00 | On Going |
26 | 2018-19 ( Ph - I ) |
Const. of Boundary Wall at Majeralga Jharnarchar Homuhia Kabarsthan | Birsing Jarua | Other | 2,45,000.00 | 1,83,750.00 | 61,250.00 | On Going |
27 | 2018-19 ( Ph - I ) |
Const. of Girls Common Room at Monirchar Reserve ME Madrassa | Birsing Jarua | Other | 1,22,000.00 | 91,500.00 | 30,500.00 | On Going |
28 | 2018-19 ( Ph - I ) |
Const. of Girls Common Room at Roshomari ME Madrassa | Birsing Jarua | Other | 1,22,000.00 | 91,500.00 | 30,500.00 | On Going |
29 | 2018-19 ( Ph - I ) |
Land Development at Uttar Kathulipara Kabarsthan | Birsing Jarua | Other | 2,45,000.00 | 1,83,750.00 | 61,250.00 | On Going |
30 | 2018-19 ( Ph - I ) |
Const. of Addl. Class Room at the premises of Birsing Maslabari ME Madrassa | Birsing Jarua | Other | 2,46,000.00 | 1,84,500.00 | 61,500.00 | On Going |
31 | 2018-19 ( Ph - I ) |
Const. of Boundary Wall at Baladoba Dhanerkuti Kabarsthan | MKR | Other | 3,92,000.00 | 3,92,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
32 | 2018-19 ( Ph - I ) |
Impv. of road from Ali Hussain House to Amin Ali House at Vill. Tumni | MKR | Other | 2,45,000.00 | 2,45,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
33 | 2018-19 ( Ph - I ) |
Infrastructure Dev. (i.e. Desk, Bench) etc. of Hazirhat High School | MKR | Other | 98,000.00 | 98,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
34 | 2018-19 ( Ph - I ) |
Const. of Boundary Wall at the premises of South Salmara Jr. College | MKR | Other | 2,94,000.00 | 2,94,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
35 | 2018-19 ( Ph - I ) |
Land Dev. at Patakata Anchalik Kabarsthan | MKR | Other | 1,96,000.00 | 1,96,000.00 | - | Fund transferred to D.C. South Salmara - Mankachar |
36 | 2018-19 ( Ph - I ) |
CONTINGENCY | 5,00,000.00 | 5,00,000.00 | - | Work Completed |